Page images
PDF
EPUB

Acts

Work authorized

Documents

July 18, 1918 Breakwater...

H. Doc. No. 431, 64th Cong., 1st sess. Sept. 22, 1922 Conditions of local cooperation modified.

Rivers and Harbors Committee Doc.

No. 4, 67th Cong., 2d sess. Jan. 21, 1927 Extending the breakwater to length of 3,000 feet.. H. Doc. No. 595, 69th Cong., 2d sess. Aug. 30, 1935 Dredging the harbor basin....

Rivers and Harbors Committee Doc.

No. 40, 74th Cong., 1st sess. Aug. 26, 1937 For the sand barrier and maintenance dredging Senate committee print, 75th Cong., 1st in the vicinity of the seaward end thereof.

sess. Mar. 2, 1945 Extending the breakwater to Round Rock H. Doc. No. 688, 76th Cong., 3d sess.

(Contains latest published map.) Mar. 2, 1945 Inner breakwater and removal of rock in fish- Report on file in Office, Chief of Englboat harbor.

neers.

Local cooperation. The act of March 2, 1945, requires that local interests grant to the United States, free of cost, necessary easements and rights-of-way and a suitable quarry or source of supply of royalty free rock for extension of the breakwater to Round Rock.

These requirements have not been complied with.
All prior requirements have been fully complied with.

Terminal facilities. There are two wharves in this harbor, which are considered adequate for existing commerce.

Operations and results during fiscal year.-A condition survey was made of the harbor. The cost and expenditures were $1,500 for maintenance.

Condition at end of fiscal year.-The project is about 37 percent complete. The work remaining to be done is the extension of the breakwater to Round Rock and the construction of the fishing boat harbor, both of which were authorized by the act of March 2, 1945. In May 1945, the controlling depth in the harbor area was 16 feet at the former tanker moorings and 12 feet to within about 150 feet from the Hobbs-Wall wharf.

The cost of the existing project to the end of the fiscal year was $796,950.03 for new work and $267,565.17 for maintenance, a total of $1,064,515.20. The expenditures were $1,064,515.20.

$ In addition, the costs and expenditures from contributed funds were $217,115.54 for new work and $27,884.46 for maintenance, a total of $245,000.

Proposed operations.-An allotment of $206,000, made in July 1945, will be applied to new work as follows: Construction of the inner breakwater and removal of pinnacle

rocks in the fishing boat harbor by contract August 1945 to January 1946

$200,000 Advance planning and preparation of plans and specifications for

the construction of the extension of the breakwater to Round Rock

6,000 Total

206, 000 The additional sum of $2,000 can be profitably expended during the fiscal year 1947 for maintenance, making a condition survey of the entire harbor.

Cost and financial summary
Cost of new work to June 30, 1945
Cost of maintenance to June 30, 1945

[blocks in formation]

Total cost of permanent work to June 30, 1945
Net total expenditures
Total amount appropriated to June 30, 1945

1, 064, 515.20 1, 064, 515. 20 1,064, 515.20

[blocks in formation]

Amount allotted from War Department Civil Appropriation

Act approved Mar. 31, 1945
Gross amount expended
Amount allotted in July 1945
Unobligated balance available for fiscal year 1946

$1,500.00

1,500.00 206, 000.00 206, 000.00

3

Amount (estimated) required to be appropriated for comple

tion of existing project : Amount that can be profitably expended in fiscal year ending

June 30, 1947, for maintenance

1, 604, 000.00

3

2, 000.00

1 Exclusive of $217,115.54 expended from contributed funds for new work.
2 Exclusive of $27.884.46 expended from contributed funds for maintenance.
3 Exclusive of available funds.

12. REMOVING SNAGS AND CLEARING CHANNELS

IN NAVIGABLE WATERS

The River and Harbor Act approved March 2, 1945, authorized the allotment of not to exceed $300,000 per year from river and harbor appropriations in removing accumulated snags and other debris, and for protecting, clearing, and strengthening channels in navigable harbors and navigable streams and tributaries thereof when such work is advisable in the interest of navigation or flood control.

An allotment of $25,000 received in the fiscal year 1945 will be applied to the removal of a shoal that has recently developed in the main channel in San Francisco Bay south of Red Rock Buoy No. 2, by Government hopper dredge July and August 1945.

Cost and financial summary

Cost of new work to June 30, 1945
Cost of maintenance to June 30, 1945

Total cost of permanent work to June 30, 1945
Net total expenditures
L'nexpended balance June 30, 1945
Total amount appropriated to June 30, 1945

$25,000 25,000

[blocks in formation]

Amount allotted from War Department Civil Appropriation Act approved June 2, 1943

$25, 000 Balance unexpended June 30, 1945

25, 000

13. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

The cost of work during the year amounted to $16,461.14; the expenditures were $18,733.91. The balance unexpended June 30, 1945, together with accounts receivable, amounting in all to $40,608.16, will be applied as needed during the fiscal year 1946 to payment of expenses incurred under this heading.

The additional sum of $35,000 can be profitably expended during the fiscal year 1947.

Cost and financial summary
Cost of new work to June 30, 1945
Cost of maintenance to June 30, 1945

$399, 051. 60 Total cost of permanent work to June 30, 1945

399, 051. 60 Plus accounts receivable June 30, 1945

2, 256. 27 Gross total costs to June 30, 1945

401, 307. 87 Minus accounts payable June 30, 1945

67.50 Net total expenditures

401, 240. 37 Unexpended balance June 30, 1945

38, 351. 89 Total amount appropriated to June 30, 1945

439, 592. 26

[blocks in formation]

Amount to be accounted for Gross amount expended

Balance unexpended June 30, 1945 Outstanding liabilities June 30, 1945

Balance available June 30, 1945
Accounts receivable June 30, 1945

Unobligated balance available June 30, 1945
Amount that can be profitably expended in fiscal year ending

June 30, 1947, for maintenance
1 Exclusive of available funds.

672607-46-pt. 1, vol. 254

57,000.00 57, 085. 80 18, 733. 91 38, 351. 89

266. 20 38, 085. 69

2, 256. 27 40, 341. 96

35,000.00 14. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES Status of all investigations for navigation called for by river and harbor acts

ARE SUBMITTED

[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors]

1 Not including $260,000 to be contributed by local interests.
? Expended for routine surveys during the fiscal year, $41.63.
* Completed.
• Expended for routine surveys during the fiscal year, $380.97.
6 This amount expended during fiscal year for routine surveys.

15. PLANT ALLOTMENT, SAN FRANCISCO, CALIF., DISTRICT

Cost and financial summary Undistributed costs June 30, 1945

$176, 903.00 Net total cost to June 30, 1945 Plus accounts receivable June 30, 1945

176, 903.00

46, 387. 74 Gross total costs to June 30, 1945 Minus accounts payable June 30, 1945

223, 290.74

226, 550.08 Net total expenditures Unexpended balance June 30, 1945

-3, 259.34

762, 028. 52 Total amount appropriated to June 30, 1945

758, 769. 18

[blocks in formation]

-1,039, 252. 71

Net amount to be accounted for Gross amount expended

$1, 131, 951. 66 Less:

Reimbursements collected $741, 551. 39
Receipts from sales 2, 191, 681. 50

2, 933, 232. 89

-1, 801, 281. 23

[blocks in formation]

and committee resolutions

[graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

16. PAJARO RIVER, CALIF. Location. The work is located on the Pajaro River at Watsonville and on Carnadero Creek at Gilroy. (See U. S. Geological Survey Quadrangles, Capitola, San Juan Bautista, and Morgan Hill, Calif.)

Existing project.—This provides for the construction of levees on the right and left banks of the Pajaro River from near the mouth to high ground, about 6 miles upstream from Watsonville, with suitable bank protection; and the raising, enlargement, and lengthening of the existing levee on Carnadero Creek at Gilroy. The estimate of cost of new work, made in 1942, is $511,160.

The project was authorized by the Flood Control Act approved December 22, 1944, and is contained in House Document No. 505, Seventy-eighth Congress, second session. The latest published map is in that document.

Local cooperation. See page 5 for requirements. Assurances of local cooperation have not been received.

Operations and results during fiscal year.–Field surveys were made and other field work performed toward the preparation of project plans. The costs were $3,683.45 for new work. The expenditures were $4,000.

« PreviousContinue »