Integrated Production, Control Systems: Management, Analysis, and DesignFocuses on the quantitative approaches necessary to computer-integrated manufacturing systems, and integrates major topics covering all phases of the production control cycle: production information processing and flow, production planning, forecasting, material requirements planning and monetary control, and scheduling. This new edition features a compendium set of 11 user-friendly computer programs for the IBM PC that enhance the teaching power of the text, allowing readers to solve real-life problems. Among programs included are growth forecasting, aggregate planning, material requirements planning, lot sizing and inventory control, and limited-resource scheduling. The chapters on scheduling give particularly thorough coverage on this difficult subject. Solutions are clearly presented, with many examples and exercises included in the text. |
From inside the book
Results 1-3 of 84
Page 266
... sequence is 2-1-3-4-5-7-8-6 , which results in the following tardiness . Task i Completion Time t¡ Due Date ... sequence chosen . The very desirable objective of minimizing makespan is accomplished by every sequence and equal to the sum ...
... sequence is 2-1-3-4-5-7-8-6 , which results in the following tardiness . Task i Completion Time t¡ Due Date ... sequence chosen . The very desirable objective of minimizing makespan is accomplished by every sequence and equal to the sum ...
Page 280
... sequence of 6-3-2-1-5-4 . For K = 2 the corresponding sequence is 3-2-1-6-5-4 . The resulting two schedules are seen in Figure 7.21 . Note that for K = 1 makespan was 36 hours and for K = 2 the makespan was 33 hours . The sequence to ...
... sequence of 6-3-2-1-5-4 . For K = 2 the corresponding sequence is 3-2-1-6-5-4 . The resulting two schedules are seen in Figure 7.21 . Note that for K = 1 makespan was 36 hours and for K = 2 the makespan was 33 hours . The sequence to ...
Page 292
... sequence three parallel machines to reduce makespan . Do this manually and with the SEQ.BAS program . Compare the results . 19. Using Data Set C , sequence three parallel machines using Algorithm 7.5 . Draw the machine - load Gantt ...
... sequence three parallel machines to reduce makespan . Do this manually and with the SEQ.BAS program . Compare the results . 19. Using Data Set C , sequence three parallel machines using Algorithm 7.5 . Draw the machine - load Gantt ...
Contents
THE ROLE OF PRODUCTION CONTROL | 1 |
PRODUCTION CONTROL | 18 |
FORECASTING | 59 |
Copyright | |
14 other sections not shown
Other editions - View all
Common terms and phrases
ACTIM activity aggregate planning algorithm allow analysis approach assembly assigned assumed BASICA batch BEGIN INVENTORY Box-Jenkins calculate carrying costs Chapter completion component considered constraints critical path cycle Data Set determine due date Equation error example problem exponential smoothing factors follows forecasted demand function function key Gantt chart given in Figure GROSS REQUIREMENTS Industrial Engineering input inventory costs inventory item inventory level KANBAN Line Balancing line-of-balance linear linear model machine makespan manufacturing master schedule MATERIAL REQUIREMENTS PLANNING maximum mean tardiness minimize minimum needed node operation optimal order costs order quantity output overtime parameters percent period personal computer procedure processor production control purchase quadratic RECPT regression regression analysis resource safety stock sequence shift shown in Figure solution step storage Tandem Computers technique total cost units values vendor week