of the dam. Reimbursements for lands and rights-of-way are to be completed.

Sepulveda Dam.-Construction of the dam and Balboa Boulevard improvement was completed in December 1941. Rights-ofway transactions are to be completed.

San Gabriel River, Santa Fe Dam to vicinity of Walnut Creek.Construction has not been started. Contract plans and specifications are partially completed.

Los Angeles River channel-Lankershim Boulevard to Niagara Street. Construction has not been started. Contract plans and specifications are partially completed.

Tujunga Wash channel.-Construction has not been started. Whittier Narrows flood-control basin.-Construction has not been started.

The total costs to June 30, 1945, for new work and for maintenance for units of the existing projects were:

[blocks in formation]

Los Angeles River channel:
Owensmouth Ave. to
Lankershim Blvd.
Lankershim Blvd. to
Santa Ana branch,
Pacific Electric Ry.
bridge.
Santa Ana branch,
Pacific Electric Ry.
bridge, to near Artesia
St

Haines Canyon.
Sycamore Wash.

Verdugo Wash.
Compton Creek

Surveys and engineering.
Tujunga Wash channel.
Burbank Western system.
Santa Fe flood-control basin.
San Gabriel River channel.
Whittier Narrows flood-con-
trol basin.

Alhambra Wash.

Rio Hondo channel, Santa
Fe Ry. to Whittier Nar-
rows flood-control basin.
Rubio Canyon diversion..
Eaton Wash

Ballona Creek channel and
jetties

[blocks in formation]
[blocks in formation]

509, 118. 38 217, 754.88 10, 391, 671. 65

Total, maintenance.

Grand total.

564, 866. 94 61, 957, 386. 39

1,759, 045. 51 217, 754.88 71, 784, 191. 10 564, 866.94

70, 899. 45

256, 113. 38

[blocks in formation]

1,829, 944 96 217,754 88 72,040, 304.48 564,866.94

72, 605, 171. 42

The total expenditures to June 30, 1945, for the units of the

[blocks in formation]

Proposed operations.-The balance unexpended on June 30, 1945, amounting to $2,615,596.45, plus an allotment of $90,000 in July, will be applied as follows:

[blocks in formation]

Preparation of project plans and detailed plans and specifications for authorized construction units of the entire project July 1, 1945 to June 30, 1946Acquisition of lands, relocation of utilities, highways, and railways, July 1, 1945, to June 30, 1946____ Preliminary studies and preparation of plans for Lopez Dam

Maintenance:

Ordinary repairs to completed sections of the Los Angeles River and tributary channels and routine maintenance and operation of Hansen and Sepulveda Dams, July 1, 1945, to June 30, 1946_

Total for all work.

$1, 285, 922. 11

736, 322. 27

434, 691. 44

90,000.00

158, 660.63

2,705, 596. 45

The additional sum of $16,900,500 can be profitably expended during fiscal years 1946 and 1947 ($5,600,500 of this total in 1946) for the following work:

Completion of Santa Fe flood-control basin and construction of San Gabriel River channel, Canyon to Santa Fe flood control basin

Partial construction of:

Los Angeles River channel.

Whittier Narrows flood-control basin_
Tujunga Wash channel___.

Total

$2,900, 500

6, 000, 000

5, 000, 000

3, 000, 000

16, 900, 500

The additional sum of $322,000 can be profitably expended during fiscal year 1947 as follows:

New work:

Design and preparation of plans for units of the project_____ $186, 000 Maintenance (operation and care):

Hansen Dam

Sepulveda Dam

Los Angeles River and tributary streams.

Total maintenance

Total for all work...

[blocks in formation]

Cost and financial summary

REGULAR FUNDS

Cost of new work to June 30, 1945.

Cost of maintenance to June 30, 1945_.

Total cost of permanent work to June 30, 1945_-.

Undistributed costs June 30, 1945.

Net total cost to June 30, 1945

Plus accounts receivable June 30, 1945_

Gross total costs to June 30, 1945. Minus accounts payable June 30, 1945.

Net total expenditures_

Unexpended balance June 30, 1945_

Total amount appropriated to June 30, 1945.

$61, 392, 519. 45 564, 866. 94

61, 957, 386. 39 -655, 985. 53

61, 301, 400. 86 106, 180. 80

61, 407, 581.66 1, 285, 922. 11

60, 121, 659.55 2, 615, 596. 45

62, 737. 256. 00

[blocks in formation]

Cost of new work.

Cost of maintenance.

Total cost..

Total expended..

9, 540, 051. 49

Allotted....

8,340, 400.00

$10,004,275.36 $8, 977, 778. 73 $8, 522, 258. 24-$1,841,457.76 $1, 164, 540.09
47, 945. 58
114, 706. 86 124,798. 62 152, 664.63
123, 623. 68
10,052, 220. 94 9,092, 485. 59 8,647,056.86 1, 994, 122. 39 1,288, 163.77
10, 543, 946. 56 8,267, 603.31
8, 245,000.00-1,162,000.00

1,536, 802. 91

1,476, 516. 12

432, 700.00

606,000.00

Balance unexpended July 1, 1944-.
Amount allotted from War Department Civil
Appropriation Act approved Apr. 28, 1942
Amount allotted from War Department Civil
Appropriation Act approved Mar. 31, 1945

Amount to be accounted for...

Deductions on account of revocation of allotment_-_.

[blocks in formation]

Net amount to be accounted for..

4, 288, 112. 57 196, 000. 00 4,092, 112. 57

[blocks in formation]

Unobligated balance available June 30, 1945--

Amount allotted in July 1945----

Unobligated balance available for fiscal year 1946--

Amount (estimated) required to be appropriated for completion of existing project

Amount that can be profitably expended in fiscal years 1946 and 1947:

[blocks in formation]

819, 549.25

90,000.00

909, 549.25

165, 900, 000.00

17,086, 500.00 136,000.00

17, 222, 500.00

1 Exclusive of available funds.

EMERGENCY RELIEF FUNDS

Cost of new work to June 30, 1945.
Cost of maintenance to June 30, 1945.

$10, 391, 671.65

Total cost of permanent work to June 30, 1945-

Undistributed costs June 30, 1945---

Net total cost to June 30, 1945

Net total expenditures--

Total amount appropriated to June 30, 1945‒‒‒‒‒

10, 391, 671.65 617, 263. 11

11, 008, 934.76 11, 008, 934. 76 11, 008, 934. 76

[blocks in formation]

CONSOLIDATED COST AND FINANCIAL SUMMARY FOR
LOS ANGELES COUNTY DRAINAGE AREA, CALIFORNIA

Cost of new work to June 30, 1945-
Cost of maintenance to June 30, 1945---

Total cost of permanent work to June 30, 1945‒‒‒‒‒ Undistributed costs June 30, 1945

Net total cost to June 30, 1945‒‒‒‒‒‒ Plus accounts receivable June 30, 1945

Gross total costs to June 30, 1945----Minus accounts payable June 30, 1945---

Net total expenditures--

Unexpended balance June 30, 1945---.

Total amount appropriated to June 30, 1945----

1

1 $71, 784, 191. 10 564, 866.94

1 72, 349, 058. 04 -38,722.42

72, 310, 335. 62 106, 180.80

72, 416, 516. 42 1, 285, 922. 11

171, 130, 594. 31

2,615, 596. 45

173, 746, 190.76

[blocks in formation]

Amount to be accounted for..

Deductions on account of revocation of allotment_

802,000.00

[blocks in formation]
[merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small]

Balance unexpended June 30, 1945--

1 Exclusive of $256,113.38 contributed funds which have been completely expended.

2,615, 596. 45

[blocks in formation]

Unobligated balance available June 30, 1945

Amount allotted in July 1945--

Unobligated balance available for fiscal year 1946___

Amount (estimated) required to be appropriated for completion of existing project 2

Amount that can be profitably expended in fiscal years 1946

and 1947:

For new work".
For maintenance

Total 2

2

2 Exclusive of available funds.

106, 180.80

819, 549.25 90,000.00

909, 549.25

165, 900, 000. 00

17, 086, 500.00 136,000.00

17, 222, 500.00

9. SANTA ANA RIVER, CALIF.

Location. These works are on the Santa Ana River and tributaries and other streams in Orange, Riverside, and San Bernardino Counties.

Existing project.-The Flood Control Act approved June 22, 1936, authorized the construction of reservoirs and related flood control works for the protection of the metropolitan area of Orange County, at an estimated construction cost not to exceed $13,000,000. The Flood Control Act approved June 28, 1938, modified the project to provide for the control of floods on San Antonio and Chino Creeks, in accordance with plans approved by the Chief of Engineers, and authorized $6,500,000 for initiation and partial accomplishment of the plans for those creeks. (See H. Doc. No. 688, 75th Cong., 3d sess.) The Flood Control Act, approved August 18, 1941, authorized the amount of $2,500,000, in addition to previous authorizations, for the prosecution of the projects approved in the above-mentioned flood-control acts, for flood control in the Santa Ana River Basin, and for the protection of Orange County in California. The Flood Control Act approved December 22, 1944, authorized the amount of $10,000,000 in addition to previous authorizations for the prosecution of the projects approved in the above-mentioned flood-control acts, including the projects on Lytle and Cajon Creeks for local flood protection at San Bernardino and Colton, Calif., in accordance with the recommendations contained in the report of the Chief of Engineers dated February 11, 1944. (See H. Doc. No. 534, 78th Cong., 2nd sess.)

The individual units considered in the general plan for this project and their estimated costs are as follows: