Page images
PDF
EPUB

Amount (estimated) required to be appropriated for completion
of existing project'
Amount that can be profitably expended in fiscal year ending
June 30, 1947 for new work

1

49, 300.00

49, 300.00

1 Exclusive of available funds.

10. CORALVILLE RESERVOIR, UPPER MISSISSIPPI RIVER BASIN, IOWA

Location. The work covered by the project is on the Iowa River in Johnson County, Iowa, approximately 83.5 miles above the mouth of the waterway which empties into the Mississippi River about 433 miles above the mouth of the Ohio River.

Existing project.-The plan of improvement provides for the construction of an earth-fill dam, 1,400 feet long at the top, rising approximately 95 feet above the stream bed, with a reservoir providing for a controlled storage of 400,000 acre-feet. The outlet works are located adjacent to the left abutment and the uncontrolled spillway is located on the right abutment with discharge from spillway entering the river about 900 feet downstream from the toe of the dam. The reservoir will accomplish almost complete control of floods and will minimize flood damages on the Iowa River from the dam to the mouth of the Cedar River. It will provide a large degree of protection for lands along the Iowa River below the mouth of the Cedar River, and significant reductions of Mississippi River flows at Keokuk, Iowa, and reduction in flows at Cairo, Ill. The existing project was selected and approved by the Chief of Engineers under the general authorization contained in the Flood Control Act approved June 28, 1938. The estimated cost of new work, revised in 1940, is $4,217,000 for construction and $1,790,000 for lands and damages.

Local cooperation.-Section 2 of the Flood Control Act approved June 28, 1938, applies.

Operations and results during fiscal year.-The work done during the fiscal year consisted of studies and investigations, by hired labor, in connection with the consideration of alternate dam sites. The costs during the year were $28,062.34 for new work. The expenditures were $29,604.43.

Condition at end of fiscal year.-Construction work has not been started. A revised design, based on the relocation of the proposed dam site, was being prepared at the close of the fiscal year. The cost to June 30, 1945, were $257,156.08 for new work. The expenditures were $256,061.87.

Proposed operations.-The balance unexpended on June 30, 1945, $35,586.35, will be applied to accounts payable June 30, 1945, $868.21, and to continuation of the advance planning by hired labor during the fiscal year 1946.

The additional sum of $62,000 can be profitably expended during the fiscal year 1947 for completion of advance planning, consisting of revision of design and preparation of contract plans and specifications, by hired labor.

[blocks in formation]

Amount (estimated) required to be appropriated for completion of existing project'

Amount that can be profitably expended in fiscal year ending
June 30, 1947 for new worki

5,715, 400.00

62, 000.00

1 Exclusive of available funds.

11. SABULA, MISSISSIPPI RIVER, IOWA

Location. The work covered by this project is on the Mississippi River at and in the vicinity of the town of Sabula, Iowa, which is 52 miles above Davenport, Iowa, and 535 miles above the mouth of the Ohio River.

Existing project. Two dikes, or levees, now protect the town from flood waters by closing the portion of an old bay which lies west of the town. The proposed improvement consists of the protection of the existing levees, which are exposed to wave wash and current wash, by riprapping at critical points. The latest (1940) estimate of cost to the United States is $25,000 for construction. The existing project was selected and adopted by the Flood Control Act approved December 22, 1944, substantially in accordance with House Document Numbered 328, Seventy-seventh Congress, first session.

Local cooperation.-Section 3 of the Flood Control Act approved June 22, 1936, applies. See page 5 for requirements. The requirements of local cooperation have not yet been fulfilled.

Operations and results during fiscal year.-None.

Condition at end of fiscal year.-No work has been done. No funds have been allotted to this project.

Proposed operations.—No operations are proposed during the fiscal year 1946.

The amount of $3,500 can be profitably expended during the fiscal year 1947 for preparation of plans and specifications, by hired labor.

12. GALENA, GALENA RIVER, ILL.

Location. The work covered by this project is on the Galena River (Fever River), Ill., at and in the vicinity of the city of Galena, located 4 miles above the river's mouth.

Existing project. The plan of improvement provides for local flood protection at Galena, Ill., by the construction of levees and flood walls with related drainage works and pumping plant; by increasing the flood channel capacity through and below the city by removing five existing bridges and modifying a sixth; and by channel excavation. The proposed improvement will give local flood protection to the city of Galena against a discharge of 25,000 cubic feet per second at that city. The latest (1940) estimate of cost is $418,000 for construction, with $4,000 annually for maintenance of the channel of Galena River through and below the city. The existing project was selected and adopted by the Flood Control Act approved December 22, 1944, substantially in accordance with House Document Numbered 336, Seventy-seventh Congress, first session.

Local cooperation.-Section 3 of the Flood Control Act approved June 22, 1936, applies. See page 5 for requirements. In addition to the usual requirements, local interests will be required to contribute $118,000 to the first cost of construction, either in cash or in credits for performance of work forming part of the project as allowed by the Secretary of War. The requirements of local cooperation have not yet been fulfilled.

Operations and results during fiscal year.-A limited amount of preliminary work was performed by hired labor during the year. The costs during the year were $75.23 for new work. The expenditures were $47.63.

Condition at end of fiscal year.-Except for minor preliminary operations, no work has been done on this project. The total cost to June 30, 1945, was $75.23 for new work. The expenditures were $47.63.

Proposed operations. The balance unexpended on June 30, 1945, $29,952.37, will be applied to advance planning, by hired labor, during the fiscal year 1946.

The additional sum of $388,000 can be profitably expended during the fiscal year 1947, as follows:

New work:

Completion of advance planning and contract plans and specifications, by hired labor

Total construction of project, by contract

Total

$6,000 382, 000

388,000

[blocks in formation]

Amount allotted from War Department Civil Appropriation Act approved Mar. 31, 1945

Gross amount expended

30,000.00 47.63

Balance unexpended June 30, 1945

Outstanding liabilities June 30, 1945

29, 952. 37 194.00

Unobligated balance available June 30, 1945

29, 758.37

Amount (estimated) required to be appropriated for completion of existing project'

388,000.00

Amount that can be profitably expended in fiscal year ending
June 30, 1947 for new work'

1 Exclusive of available funds.

13. ELKPORT, TURKEY RIVER, IOWA

388,000.00

Location. The work covered by this project is on the Turkey River in northeastern Iowa at the town of Elkport, which is at the junction of Elk Creek and Turkey River, 21.2 miles above the mouth of Turkey River at the Mississippi River near Guttenberg, Iowa.

Existing project. The plan of improvement provides for local flood protection at Elkport by the construction of a levee. The latest (1941) estimate of cost is $18,000 for construction including $5,000 to be contributed by local interests. The existing project was authorized by the Flood Control Act approved December 22, 1944, substantially in accordance with House Document Numbered 700, Seventy-seventh Congress, second session.

Local cooperation.-Section 3 of the Flood Control Act approved June 22, 1936, applies. See page 5 for requirements. In addition to the usual requirements, local interests will be required to contribute the sum of $5,000 toward the cost of construction. The requirements of local cooperation have not yet been fulfilled. Operations and results during fiscal year.—None.

Condition at end of fiscal year. No work has been done. No funds have been allotted to this project.

Proposed operations.-No operations are proposed during the fiscal year 1946.

The sum of $13,000 can be profitably expended during the fiscal year 1947, as follows:

New work:

Advance planning, consisting of preparation of definite project report, and contract plans and specifications, by hired labor-Total construction of project, by contract

Total

[blocks in formation]

14. UPPER MISSISSIPPI RIVER BASIN, ROCK ISLAND DISTRICT Location. The Mississippi River Basin above the Ohio River, exclusive of the Missouri River Basin, in the Rock Island district. Existing project.-The Flood Control Act of June 28, 1938, approved the general comprehensive plan for flood control and other purposes in the Upper Mississippi River Basin described in Flood Control Committee Document No. 1, Seventy-fifth Congress, first session, with such modifications thereof as in the discretion of the Secretary of War and the Chief of Engineers may be advisable, and authorized $6,600,000 for reservoirs and $2,700,000 for local flood-protection works on the upper Mississippi and Illinois Rivers; the reservoirs and local protection projects to be selected and approved by the Chief of Engineers. The act approved June 28, 1938, specifically provides that the authorization shall include the enlargement and extension of a system of levees located on the south side of the Sangamon River east of Chandlerville, Ill., as set forth in House Document No. 604, Seventy-fifth Congress, third session. The Flood Control Act of December 22, 1944, authorized to be appropriated the additional sum of $10,000,000 for prosecution of the comprehensive plan, including the Red Rock Reservoir on the Des Moines River. The following individual projects located in the Rock Island district were considered in the comprehensive plan:

[blocks in formation]

1 See individual report for details of project. Substituted by the Flood Control Act approved Dec. 22, 1944 for the site originally considered at Howell.

Local cooperation.-See page 5 for requirements.

Operations and results during fiscal year.-As shown on individual reports for Union Township Drainage District Levee, Coralville Reservoir, and Red Rock Reservoir.

Condition at end of fiscal year.-As shown in individual reports. Proposed operations.-As shown in individual reports.

« PreviousContinue »