... GATES The sluiceways at each end of the dam , from which the canals take their supply , were built through the same pattern and consist of a series of horizontal plate guides spaced vertically and supporting the water - tight skin ...
... GATES The sluiceways at each end of the dam , from which the canals take their supply , were built through the same pattern and consist of a series of horizontal plate guides spaced vertically and supporting the water - tight skin ...
Page 6
... gate of the same size as the others supplies water to a small ditch . The Taintor gates and the west head gates are all operated by one gasoline engine of 8 horsepower . The dam will raise the level of the water about 6 feet above its ...
... gate of the same size as the others supplies water to a small ditch . The Taintor gates and the west head gates are all operated by one gasoline engine of 8 horsepower . The dam will raise the level of the water about 6 feet above its ...
Page 7
... Gates and machinery . Time of construction . Distance from railway . Approximate cost . Unit Percha Dam Mesilla Dam Cubic yards . ..do .. 23 , 367 22 , 632 7,331 5 , 626 .do . 32,000 4,553 Linear feet . 7,506 Cubic yards . 4,546 2,876 ...
... Gates and machinery . Time of construction . Distance from railway . Approximate cost . Unit Percha Dam Mesilla Dam Cubic yards . ..do .. 23 , 367 22 , 632 7,331 5 , 626 .do . 32,000 4,553 Linear feet . 7,506 Cubic yards . 4,546 2,876 ...
Page 8
... gates and the roller crest . The cost of the several designs was found to be not very far apart and which the entire ... gates , each 7 feet square . These gates are operated by a line shaft installed on the head - wall platform . The ...
... gates and the roller crest . The cost of the several designs was found to be not very far apart and which the entire ... gates , each 7 feet square . These gates are operated by a line shaft installed on the head - wall platform . The ...
Page 9
... gate is 8 feet 4 inches lower than the sill of the intake gates and the entrance to the sluiceway is 6 feet 4 inches lower , thus permitting water to be drawn into the canal from the upper stratum and causing the silt to be deposited in ...
... gate is 8 feet 4 inches lower than the sill of the intake gates and the entrance to the sluiceway is 6 feet 4 inches lower , thus permitting water to be drawn into the canal from the upper stratum and causing the silt to be deposited in ...
Other editions - View all
Common terms and phrases
American Falls Dam arch Arrowrock Arrowrock Dam back fill balanced needle valves bars Boise project borrow pits built Bureau of Reclamation buttresses canyon cement cent channel clay cobbles cofferdams completed conduit construction contracting officer contraction joints contractor core wall cost Creek crest crete cubic yards cut-off trench depth discharge downstream face drainage drains drawings drilled earth elevation embankment emergency gate engineer excavation fault zone foundation furnished Government gravel grout holes hauling hoist Illus included installed irrigation located material maximum ment metal miles North Platte project operation Owyhee Dam paint paragraph Pathfinder Dam penstock pipe pits placed plant portion pressure grouting railroad reservoir riprap river roller sand schedule second-feet shaft shown side slope sluice sluiceway solid rock specifications spillway storage stream bed structure suitable surface thickness timbering tion tracting officer Trash Rack unit prices bid upstream face vertical Weber River