Boulder Canyon Project: Final Reports

Front Cover
United States Department of the Interior, Bureau of Reclamation, 1947 - Arch dams
 

Contents

Bibliography
24
CHAPTER IIDIVERSION TUNNELS 11 Preliminary statements
25
GENERAL INFORMATION 12 The plan
26
Streamflow data 14 Tunnel capacity
27
SECTION
28
Drill carriage
30
Construction adits
32
Top headings
33
Drilling main headings
34
Blasting 21 Removing broken rock
37
Disposal of material
39
Scaling tunnel walls
40
Excavating invert sections
41
Compressedair requirements
42
26
43
Ventilation
44
Rates of progress PAGE
45
General discussion
47
Forms and equipment
49
Placing concrete lining
56
Tunnelplug keyways
60
Cofferdams at portals PAGE 47 49 56 60
61
Concrete operations 34 Rates of progress
63
GROUTING AND DRAINAGE 35 General
64
Grouting
67
Equipment
69
Drainage
72
COST SUMMARY DIVERSION TUNNELS 74 A NOSI 65 69
74
CHAPTER IIICOFFERDAMS 39 Introductory statements
77
General description
78
Protection of excavation 42 Acceptance of cofferdams
80
Classification of excavation 44 Earth and rock embankments
81
Upstream cofferdam Downstream cofferdam DESIGN 77 78 80 80 81 81
82
Temporary cofferdams 48 Draining the dam site 49 River flow during diversion 51
92
Downstream cofferdam 50 Upstream cofferdam
98
Construction cost
100
CHAPTER IVDIVERSION TUNNEL CLOSURE STRUCTURES RIVER CONTROL DURING CONSTRUCTION 53 Tentative program
101
Actual program
103
DIVERSION TUNNEL CLOSURE GATES 55 Preliminary design studies
104
Final design of gates
105
Gate structure
111
ii
115
Assembly and erection of gates 69 59 Closure of Arizona gate
116
Closure of Nevada gate UPSTREAM TUNNEL PLUGS 61 General description
118
101
119
Cooling and grouting concrete
123
Construction methods
124
Inner Arizona tunnel plug
129
Nevada tunnel plugs
130
Outer Arizona tunnel plug 68 Installation of outlet gates COST SUMMARY CLOSURE STRUCTURES
132
CHAPTER VINTAKE TOWERS 69 General description
137
Preliminary studies
142
Location of towers 72 Stability against earthquakes
143
Design of towers
146
Inlet ports
147
Cylinder gates
150
Gate hoists
151
Operating houses 78 Intake tower bridges
153
Emergency gates
155
Trashracks
156
vi
157
Placing concrete
159
Gate installation
164
CHAPTER VIPENSTOCK AND OUTLET TUNNELS SECTION PAGE 87 General description
169
DESIGN
172
Lower penstock tunnels
173
Upper header tunnels
174
Upper penstock tunnels
175
Outlet tunnels
176
Inclined tunnels
177
Upper header tunnels
178

Common terms and phrases

Popular passages

Page 81 - Rock excavation, including all solid rock in place which could not be moved until loosened by barring, wedging, or blasting, and all boulders or detached pieces of solid rock more than one cubic yard in volume. Solid rock under this class, as distinguished from soft or disintegrated rock under common excavation, was defined as sound rock of such hardness and texture that it could not be effectively loosened or broken down by hand drifting picks.
Page 82 - The largest rock in the rock fill shall be not more than 1 cu. yd. in volume. The inclusion of gravel or rock spalls in the mass in an amount not in excess of that required to fill the voids in the coarser material shall be required.
Page 201 - ... section CC) by vertical endless trains or belts of rollers that extend throughout practically the entire height of the gate leaf and its follower ring. The leaf is lowered in closing until the bronze seal ring affixed to the downstream face of its bulkhead portion is brought into horizontal alignment with the mating bronze seat ring enclosing the water passageway in the adjacent face of the downstream gate frame, whereupon further downward movement of the gate leaf is arrested by lugs on the...
Page 80 - ... cut-off trenches and other parts of the work free from water as required for constructing each part of the work.
Page 201 - J£ in. When this has been accomplished, the toggles connecting the leaf and the crosshead are fully extended, whereupon the gate leaf with its ring follower, the two inclined roller trains, and the two roller carriages all move upward as a unit until such time as the ring follower is brought into axial alignment with the water passage or conduit, when limit switches stop the hoist nnd the upward movement ceases and the opening cycle is then completed.
Page 201 - ... contact between seating and sealing surfaces ever occurs while these gates are passing through their opening or closing cycles of operation, and in consequence those surfaces are not subjected to the rapid wear and deterioration that occurs when sliding contact under high-intensity loadings is present. Inasmuch as all movements of the gate leaf occur while it is supported and transported on the roller-train systems as described, the force or power input required to operate it is relatively small....
Page 17 - The rodman was lowered by %-inch rope, snubbed around two drills driven securely into crevices in the rock. When he reached the river's edge, he removed the rope and returned by trail and ladders to the top. While one rodman was returning, another was being lowered at a different location. In making the survey, about 4,000 points were located in one section of the canyon wall having a horizontal area of 330 feet by 660 feet, the greater dimension being parallel to the river.
Page 309 - Sb, the latter being projected to the horizontal as shown. Numerical values for the dimensions were determined at various points along the transition, based on the size of water area, plus a desired air area, required for the flowing stream. The water area, which contracts as...

Bibliographic information