Page images
PDF
EPUB

700 linear feet of log foundation 50 feet wide will probably be required at the outer end.

30, 456 tons of stone, at $1.12

700 feet of log foundation, at $8

Add about 15 per cent. for supervision and contingencies...

[blocks in formation]

The following estimate of cost of dredging a channel 16 feet deep at mean low water and 400 feet wide through Fort Hale Bar-about 7,000 feet longis based upon the survey of 1886:

Dredging 450,000 cubic yards of mud, at 9 cents.....
Add about 15 per cent. for supervision and contingencies...

$40,500

6,500

[ocr errors][merged small]

The total required for completion of the dike and for dredging on Fort Hale Bar is $93,000; to this should be added an estimate of $5,000 annually for maintenance of channels and for repair of dike. Appropriations for the improvement of New Haven Harbor have been made as follows, viz:

[blocks in formation]

New Haven, the port of entry for the collection district of New Haven, is situated at the head of New Haven Harbor, about 3 miles from Long Island Sound. There is a light-house on Southwest Ledge at the mouth of the harbor. Fort Hale, 2 miles below the city, commands the channel.

[blocks in formation]

July 1, 1887, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1886

$136.24 20,000.00

20, 136. 24

12, 317.31

July 1, 1887, amount available

7,818.93

(Amount (estimated) required for completion of existing project.... Amount that can be profitably expended in fiscal year ending June 30, 1889 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

93,000.00 93, 000, 00

[blocks in formation]

Abstract of bids for extending dike in New Haven Harbor, Connecticut, opened at Engineer Office, U. S. Army, New York, October 13, 1886.

[blocks in formation]
[blocks in formation]

*Entered into contract October 27, 1886; contract completed May 10, 1887.

Abstract of bids for extending dike in New Haven Harbor, Connecticut, opened at Engineer Office, U. S. Army, New York, June 16, 1887.

[blocks in formation]

*Contract awarded to Owen J. Conley, to be executed in July, 1887.

COMMERCIAL STATISTICS FOR THE CALENDAR YEAR OF 1886.
Foreign commerce.

Value

Imports

Exports..

Revenue receipts

Vessels entered from foreign ports, 35; vessels cleared for foreign ports, 20.

$580,054. 16 1, 349, 655. 06 257, 811.64

[blocks in formation]

Rates of freight have been reduced more than one-half since the harbor improvements began, most of which is due to competition. The present commerce of the harbor could not, however, now be carried on were the channel in its original unimproved condition.

D 6.

CONSTRUCTION OF BREAKWATER AT NEW HAVEN, CONNECTICUT.

PROJECT.

The importance of a harbor of refuge at the entrance to New Haven Harbor had been urged by memorials to Congress, and set forth in annual reports to the Chief of Engineers, when, March 3, 1879, the first appropriation was made for the construction of a breakwater. The subject was referred to the Board of Engineers for Fortifications and for River and Harbor Improvements, who presented to the Chief of Engineers their views upon the matter in a letter dated November 24, 1879, which is printed in full in the Annual Report of the Chief of Engineers for 1880, Part I, pages 448-156. This letter presents estimates for two breakwaters to form a harbor of refuge for vessels of 20 feet draught; the easterly break water, 3,300 feet long, to extend from the light-house on Southwest Ledge to Quixe's Ledge; the westerly one, about 4,200 feet long, to extend in a general northwesterly direction from Luddington Rock, its precise location and length not being determined. Both were to be of rip-rap granite, reaching 6 feet above mean high water, 12 feet wide on top, with outer slope of 1 in 3, and inner slope of 2 in 3; the average height of the east breakwater was estimated at 32 feet, of the west one, 28 feet, and their cost was estimated at:

[blocks in formation]

The letter of the Board of Engineers was submitted by the Chief of Engineers to the Secretary of War, with the suggestion that the appropriation' then available "be applied toward the construction of a breakwater from Light-House Ledge" (the east breakwater), which was approved by him January 31, 1880. A modification of the cross-section, making the outer slope 1 on 2 and the inner slope 1 on 1, was proposed by the officer in charge and approved by the Chief of Engineers, February 14, 1880, before work was begun. This would reduce the estimate for the east breakwater to $480,000, but as the location and length of the west breakwater are not yet fixed, its cost may be greater than was estimated, and it seems advisable to retain the total estimate first given, $1,311,134.

Under this project up to July 1, 1886, 2,147 linear feet of the east breakwater were built, using 189,898 tons of granite and costing (supervision, etc., included) about $100 per linear foot.

OPERATIONS DURING THE FISCAL YEAR ENDING JUNE 30, 1887.

Under the appropriation of $75,000 made by act of Congress approved August 5, 1886, proposals were received and a contract, dated October 22, 1886, was entered into with T. J. Allen, of New York City, to deliver 57,000 tons of granite in the east breakwater at the rate of $1.12

per ton. Work was begun December 21, 1886, and up to July 1, 1887, 22,643 tons had been delivered, building 265 linear feet of the breakwater. Work is still in progress under this contract, which expires August 31, 1887.

PRESENT CONDITION OF WORK.

The east breakwater is now 2.412 feet long, being about three-quarters of its projected length of 3,300 feet. It contains 212,541 tons of granite and has cost (supervision, etc., included) about $100 per linear foot.

PROPOSED OPERATIONS.

In their report of November 24, 1879, submitting plans and estimates, the Board of Engineers expressed "the opinion that after the completion of a certain portion of the easterly breakwater the westerly one should be promptly commenced." About $65,000 will be required to finish the east breakwater.

With future appropriations it is proposed, first, to complete the east breakwater and then to begin upon the west one. Should sufficient appropriation be made, work on both could be readily prosecuted at the same time. During the ensuing year $500,000 could be profitably expended in completing the east breakwater and beginning work upon the west one.

Appropriations for the New Haven Breakwater have been made as follows, viz:

[blocks in formation]

New Haven, the port of entry for the collection district of New Haven, is situated at the head of New Haven Harbor, about 4 miles north of the breakwater. There is a light-house on Southwest Ledge, at the west terminus of the east breakwater. Fort Hale, 2 miles north from the breakwater, commands New Haven Harbor.

Money statement.

July 1, 1886, amount available......

Amount appropriated by act approved August 5, 1886

July 1, 1837, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1886

July 1, 1887, outstanding liabilities...

July 1, 1887, amount available.....

[blocks in formation]

Amount (estimated) required for completion of existing project...... 1,016, 134. 00 Amount that can be profitably expended in fiscal year ending June 30, 1889.

Submitted in compliance with requirements of sections 2 of river and

harbor acts of 1866 and 1867.

500,000.00

Abstract of bids for extending breakwater at New Haven, Conn., opened at Engineer Office, U. S. Army, New York, October 13, 1886.

[blocks in formation]

COMMERCIAL STATISTICS FOR CALENDAR YEAR OF 1886.
Vessels passing New Haven Breakwater.

[blocks in formation]

These figures are not complete, as many vessels would pass unobserved in night or in thick weather.

The value of the cargoes of the vessels can not be ascertained; it is undoubtedly very great.

D 7.

IMPROVEMENT OF MILFORD HARBOR, CONNECTICUT.

This harbor is on the north shore of Long Island Sound, about 9 miles southwest of New Haven, Conn. It consists of a broad, open bay, from the head of which a small tidal stream extends three-quarters of a mile inland to the Milford wharves.

The original depth on the bar at the mouth of the river was 2 feet at mean low water, and in some places between there and the upper wharves low tide left the channel nearly bare.

PROJECTS FOR IMPROVEMENT.

In 1872 a "survey of breakwater at Milford, Conn.," was ordered. There being no break water, a survey of the harbor for a break water was made, and in the report, dated December 24, 1872, the following plan of improvement was submitted:

1. A rip-rap breakwater from Welch's Point, on the east side of the mouth of the harbor.............

Superintendence.

Total.....

4. A jetty on the east side of the channel to prevent the dredged area filling and to confine the action of the tide...

3. Dredging 4 feet deep and 100 feet wide across the bar at the mouth of the river

2. Protecting the bluffs on the east shore from erosion, by means of small stone jetties..

$67,000

5,500

6,250

5,000

1,250

85,000

« PreviousContinue »