CONCRETE PIERS AND ANCHORS (Continued)
constructed in advance of the time of conduit installation, when the support fixtures are grouted in place. The base of the pier should be placed below the frost line.
.34 For conduits supported above ground or in open tunnels, anchors are required at all bends subjected to forces exceeding the resistance of the weight of the section of conduit and water supported at the bend. Anchors are also required about midway between expansion joints where there are two or more expansion joints between two bends requiring anchorage. This condition occurs when the distance between any two bends requiring anchors is in excess of about 500 feet, as it is desirable to limit the distance between expansion joints to a value that will keep the longitudinal forces at the anchors within practicable limits. They may be of the type shown in Figure 43 or they may completely encase the conduit as shown in Figure 44.
Conduits placed underground usually require anchors at short-radius horizontal bends with intersection angles which will produce forces exceeding the fric- tional and compressive resistance of the soil, at vertical bends at summits, and at bends adjacent to power plants and pumping plants. Where buried con- duits are laid with horizontal and vertical curves of very large radius, anchors usually are not necessary.
The forces at an anchor may be estimated by use of the formulas in Figure 45. These forces should be calculated for both the expanding and contracting con- dition with the pipe both full and empty. Wind and earthquake loads should also be considered where conduits are above ground. The resultant of all forces, including the reaction at the anchor and the weight of the anchor, under the most unfavorable conditions should intersect the base within the kern to avoid tension in the concrete (see Paragraph 2.33). The vertical component of the resultant of all forces should not be less than the horizontal component of the resultant of all forces divided by the coefficient of sliding friction at the base of the anchor. The friction coefficient may vary from 0.35 to 0.65 under dif- ferent soil conditions. Where conduits are buried the position of the resultant of all forces is not important, and a friction coefficient of 1.00 may be used. Anchors should preferably be placed on a rock base if possible. The bottom of the anchor should be extended below the lowest frost line in areas subject to freezing. As actual forces may vary on both sides of an anchor from the com- puted forces, such possibilities should be considered in proportioning the anchor. At points where computations indicate a balance of forces and where theoretically no anchors are required, it is desirable to provide at least a nominal size anchor to prevent displacement due to reasons stated above.
FABRICATION AND INSTALLATION
.35 Steel conduits are usually fabricated in courses, each course having a length equal to the net plate width after trimming. Figure 46 shows courses for a 15- foot penstock during fabrication. A number of courses are welded together to form laying sections of the lengths required. End plates of pipe sections should be prepared for field welding in accordance with the specifications. The lengths of the courses are usually made optional with the fabricator. The number of longitudinal joints in each course should be as small as practicable, taking into consideration plate lengths available. Fabrication and welding procedures should be in accordance with the applicable requirements of the API-ASME Code unless departures from the Code are desirable in special cases. All shop welding is required to be performed under full procedure control on automatic welding machines as shown in Figure 47 where possible. Hydrostatic pressure tests at a pressure equal to about 1-1/2 times the working pressure are usually required. Butt-welded longitudinal joints in penstocks and large pump-discharge lines, are usually radiographed in accordance with the provisions of the Code. Figure 48 shows a portable X-ray machine used for the radiographic inspection of shop welds.
FABRICATION AND INSTALLATION (Continued) Transportation problems usually determine whether conduits are fabricated in the contractor's shop or at the site of installation. As transport by rail of conduits over 12 feet in diameter is usually not feasible, conduits of such size should be fabricated in a field fabricating plant near the site of installation, either from plates shipped directly from the mill or from plates prefabricated at the contractor's home plant. Figure 49 shows a portion of the field fabricating plant used for the 22-foot penstocks at Davis Dam. The plates were prefabricated, cut to size, edged and rolled, then transported to the field fabricating plant for completion. Internal spiders were used during fabrication to keep the pipe courses circular until the stiffeners were welded on.
.36 The installation of steel conduits is frequently performed under a separate contract. Where this is the case it is necessary to define the length of the pipe sections and the edge preparation for the field joints so that the amount of work to be done under each contract can be determined. It is also essential in such cases to specify the permissible tolerances in pipe lengths, trueness of ends, out-of-roundness, clearances in bell-and-spigot joints and in expansion joints, spacing of supports, etc.
Conduit sections are usually transported from the nearest railroad station or from the field fabricating plant to the site of installation by truck, trailer, or barge. Figures 50 and 51 show the transport by truck and trailer of 18- and 22-foot penstock sections at Grand Coulee and Davis Dams, respectively, and Figure 52 shows the transport by barge of an 18-foot penstock section at Grand Coulee Dam from field fabricating plant to dam. Upon arrival at the site of installation the conduit sections are lifted in place by cableway, derrick, or other means suited to the site. Figure 53 shows handling by cableway of a 15- foot penstock section at Shasta Dam, and Figure 54 shows handling by derrick barge of an 18-foot penstock section at Grand Coulee Dam. Figure 55 shows handling by whirley of a 22-foot penstock section at Davis Dam, and Figure 56 shows its placement in the 27-foot octagon blockout in the intake structure.
After being set to line and grade on temporary supports, the conduit sections are first tack-welded into the line, before the joints are completely welded. Figure 57 shows the installation of the Shasta penstocks. All field welding is performed manually. After welding, the girth joints may or may not be radio- graphed de ending on the load carried by the girth joints or on the importance of the conduit. For long-span crossings, as shown in Figure 58 of the Shoshone River Siphon having a center span of 150 feet, radiographic inspection may be advisable as the girth joints are subjected to very high beam stresses. For conduits which are hydrostatically tested after installation and where girth joints are subjected only to normal stresses, radiographic inspection may be omitted. Special portable X-ray machines as shown in Figure 59 are used for the radiographic inspection. The machines are provided with rubber wheels and are moved from joint to joint on the inside of the conduit. For conduits on steep slopes, special scaffolding is required to make the welds accessible. Where a proof hydrostatic pressure test is called for, such test should follow the radiographic inspection. A test pressure of 1-1/2 times the operating pressure is usually applied by means of pumps and held for a sufficient time to permit the inspection of all parts of the conduit.
Installations in tunnels or concrete blockouts are more complicated, due to limited clearances around the conduit which may require that all welding be performed from the inside of the conduit against a backing strip. If such con- duits are to be backfilled with concrete, all welding, weld tests, and pressure tests should be completed and the exterior surfaces of the conduit cleaned before backfilling.
.37 Among the possible nondestructive tests and inspections some of the following may be required by the Bureau of Reclamation to insure a safe welded job: A. Physical and chemical tests of plates, at mills.
F. Strain-gage measurements of peening operations in special slip-joints. G. Hydrostatic pressure tests of individual pipe sections.
H. Soap or compressed-air leakage tests.
I. Hydrostatic pressure test of entire installation.
In order to insure compliance with the requirements, all operations, both in shop and field, should be subject to careful and rigid inspection by qualified welding inspectors. Inspection requirements are covered in the Bureau's Arc-Welding Manual.
.38 Periodic painting will increase the useful life of steel pipe. The accepted practice calls for cleaning of the pipe surface to bright metal by blasting, the application of one coat of cold coal-tar primer followed by one coat of hot coal- tar enamel on the inside and on the outside of pipe to be buried. The outside of exposed pipe should be given two coats of synthetic red lead followed by one coat of aluminum paint. The hot enamel coating should preferably be applied by centrifugal casting where possible. About 9 inches of each end of pipe sec- tion should be primed but left without enamel coating for field welding of the joints. The paint and the method of application should be in accordance with the American Water Works Association Standards 7A.5-1940.
.39 A cement-mortar lining of 1/2-inch thickness, applied on the inside of steel pipe in the shop by spinning, may be used in lieu of painting. The lining should be given a steel-troweled or smoothing bar finish. Before lining, the pipe should be cleaned by blasting to bright metal. No steel reinforcement is nec- essary. At each end of a pipe section about 6 inches of the lining should be omitted for field welding of the joint. After the lining has been cured, internal bracing should be placed at the uncoated ends and elsewhere if necessary to limit out-of-roudness to one-half percent on the pipe diameter. Bends, fittings, and specials, which cannot be mortar-lined by spinning, may be lined by the gunite method. A gunite coating of 3/4-inch thickness, reinforced with 2 by 4, 12-gage steel wire mesh may be applied in the shop on the outside of pipe to be buried, as shown in Figure 60. For highly corrosive soils gunite may be applied over a coal-tar enamel coating. About 12 inches at each end of pipe section should be left uncoated to facilitate field welding of the joint. Tentative Specifications 7A.7 of the American Water Works Association give further data on cement-mortar protective coating of steel pipe of sizes 30 inches and over.
Field joints where the protective lining and coating was omitted should be cleaned and painted or gunited, as the case may be, after welding and testing is completed.
« PreviousContinue » |