Design and construction: Bull.1. General features. Bull.2. Boulder Dam. Bull.5. Penstocks and outlet pipes. Bull.6. Imperial Dam and desilting works

Front Cover
United States Department of the Interior, Bureau of Reclamation, 1947 - Arch dams

From inside the book

Contents

Forms and equipment
49
Placing concrete lining
56
Tunnelplug keyways
60
Cofferdams at portals
61
49 56 60 Concrete operations 34 Rates of progress
63
GROUTING AND DRAINAGE 35 General
64
Grouting
67
Equipment 38
69
Drainage
72
NOS 65 69 72 COST SUMMARY DIVERSION TUNNELS
74
CHAPTER IIICOFFERDAMS 39 Introductory statements
77
General description
78
Protection of excavation 41 42 Acceptance of cofferdams
80
Classification of excavation 44 Earth and rock embankments
81
45
82
46
85
Upstream cofferdam Downstream cofferdam 47 Temporary cofferdams
88
Draining the dam site
90
River flow during diversion
92
Upstream cofferdam
94
Downstream cofferdam
98
Construction cost
100
DESIGN
104
Final design of gates
105
Gate structure
111
Assembly and erection of gates
116
Closure of Nevada gate
118
Design of plugs
119
Cooling and grouting concrete
123
Construction methods
124
Inner Arizona tunnel plug
129
Nevada tunnel plugs
130
Outer Arizona tunnel plug
132
77
134
CHAPTER VINTAKE TOWERS DESIGN 69 General description
137
Preliminary studies
142
Location of towers
143
Design of towers
146
Inlet ports
147
Cylinder gates
150
Gate hoists
151
78
153
Emergency gates
155
80
156
82
157
Placing concrete
159
Gate installation
164
CONSTRUCTION
166
Construction items and costs
168
CHAPTER VIPENSTOCK AND OUTLET TUNNELS SECTION PAGE 87 General description
169
SS 90
170
Construction adits
172
Lower penstock tunnels
173
Upper header tunnels
174
92
175
94
176
Inclined tunnels
177
Upper header tunnels
178
Penstock tunnels
182
98
184
CHAPTER IVDIVERSION TUNNEL CLOSURE STRUCTURES
186
Rear walls
205
Front and end walls
206
Roof
208
AUXILIARY EQUIPMENT 112 Electric power supply
211
Lighting
212
Valve house cranes
213
Telephone
214
Excavation
215
Installation of gates and valves
218
Quantities and costs
221
CHAPTER VIIITUNNELPLUG OUTLET WORKS 123 General description
223
DESIGN OF STRUCTURES 124 Tunnel plugs
227
Valve chambers
229
Transition structures
232
Observation platforms
234
Adits to valve houses
235
VALVES AND GATES 130 Needle valves
236
Operating program
237
Control and interlocking provisions
238
Lighting
239
Unwatering and drainage pumps
241
Excavation
242
Concrete placement
244
Installation of valves and gates
245
Grouting and drainage
246
Cost summary
247
Operating house utilities
252
Construction
253
CHAPTER IXSPILLWAYS INTRODUCTORY MATERIAL SECTION PAGE 147 General description
255
Geology of spillway sites
261
PRELIMINARY DESIGNS 149 Early tentative designs
264
Gloryhole spillway
266
1000
267
Sidechannel spillway with free crest
268
Sidechannel spillway with Stoney gate
270
Stoneygate spillway
273
Sidechannel spillway with siphon crest
274
Tests of model M1
275
Semifinal designs and model studies
278
FINAL DESIGNS 158 General
280
Piers and aeration
282
Weir crest
285
STRUCTURAL DESIGN 163 Spillway weirs
287
Piers
292
Drum gates
294
Gate operation
296
Operation and maintenance facilities
297
Side channels
299
Inclined tunnels and transitions
304
Foundation grouting
313
Drainage
316
Approach channel protection
317
Contraction joint grouting
318
Excavation
323
Foundation grouting
324
Placement of concrete
325
Drum gate installations
333
Arizona highway bridge
335
Grouting weir joints
337
Spillway tunnel outlet structures
339

Other editions - View all

Common terms and phrases

Popular passages

Page 82 - The largest rock in the rock fill shall be not more than 1 cu. yd. in volume. The inclusion of gravel or rock spalls in the mass in an amount not in excess of that required to fill the voids in the coarser material shall be required.
Page 81 - Rock excavation, including all solid rock in place which could not be moved until loosened by barring, wedging, or blasting, and all boulders or detached pieces of solid rock more than one cubic yard in volume. Solid rock under this class, as distinguished from soft or disintegrated rock under common excavation, was defined as sound rock of such hardness and texture that it could not be effectively loosened or broken down by hand drifting picks.
Page 17 - The rodman descended from the opposite canyon rim in a vertical line to the river's edge, stopping at points required for accurately delineating the canyon wall surface. Horizontal and vertical angles were read at both transits for each designated point. Over most of the area surveyed, the rodman was lowered by ropes in order to reach otherwise inaccessible places. A 15-foot pole, with a flag attached at one end, was used to reach the back of caves or below overhanging cliffs ; but in many instances...
Page 17 - The rodman was lowered by %-inch rope, snubbed around two drills driven securely into crevices in the rock. When he reached the river's edge, he removed the rope and returned by trail and ladders to the top. While one rodman was returning, another was being lowered at a different location. In making the survey, about 4,000 points were located in one section of the canyon wall having a horizontal area of 330 feet by 660 feet, the greater dimension being parallel to the river.
Page 81 - ... soft or disintegrated rock under common excavation, is defined as sound rock of such hardness and texture that it can not be effectively loosened or broken down by hand drifting picks. Common excavation.— All material required to be excavated except solid rock, including earth, gravel, and also indurated material of all kinds such as hardpan, cemented gravel, and soft or disintegrated rock, which may require blasting before removal by team-drawn scrapers or excavating machinery; also all...

Bibliographic information