Cases Decided in the Court of Claims of the United States, Volume 103U.S. Government Printing Office, 1946 - Law reports, digests, etc |
From inside the book
Results 1-5 of 100
Page 36
... question of expenditures for refugee Indians . The second claim is for an unexpended balance of $ 2,000 under a treaty obligation of September 20 , 1816 , the obliga- tion having been duly appropriated for . Recovery is due in the sum ...
... question of expenditures for refugee Indians . The second claim is for an unexpended balance of $ 2,000 under a treaty obligation of September 20 , 1816 , the obliga- tion having been duly appropriated for . Recovery is due in the sum ...
Page 43
... question that Congress did not authorize the disbursement ; the defendant concedes that ; but to recover the fees now would constitute a gratuity under the Act of August 12 , 1935 , 49 Stat . 571 , 596. Transmittal of the funds to the ...
... question that Congress did not authorize the disbursement ; the defendant concedes that ; but to recover the fees now would constitute a gratuity under the Act of August 12 , 1935 , 49 Stat . 571 , 596. Transmittal of the funds to the ...
Page 46
... question ; and where no portion thereof was paid to the Chickasaw Nation ( 94 C. Cls . 215 , 222 , finding 15 ) ... questions : First , the date of taking by the Government of 136,204.02 acres by reason of an erroneous survey which was ...
... question ; and where no portion thereof was paid to the Chickasaw Nation ( 94 C. Cls . 215 , 222 , finding 15 ) ... questions : First , the date of taking by the Government of 136,204.02 acres by reason of an erroneous survey which was ...
Page 47
United States. Court of Claims. 45 Reporter's Statement of the Case These questions were considered and decided by ... question were taken by the defendant , as found by the court , 94 C. Cls . 215 , on March 3 , 1875 . 2. The value of ...
United States. Court of Claims. 45 Reporter's Statement of the Case These questions were considered and decided by ... question were taken by the defendant , as found by the court , 94 C. Cls . 215 , on March 3 , 1875 . 2. The value of ...
Page 54
... question of value on March 3 , 1875 of the 136,204.02 acres of land owned jointly by the Chickasaw and Choctaw nations and taken by the defendant on that date . The case was originally tried , argued , and submitted on the questions of ...
... question of value on March 3 , 1875 of the 136,204.02 acres of land owned jointly by the Chickasaw and Choctaw nations and taken by the defendant on that date . The case was originally tried , argued , and submitted on the questions of ...
Other editions - View all
Common terms and phrases
acres Act of June agreement amount approved August August 11 back counters building caisson cents change order Chickasaw Nation Chief of Engineers Choctaw cofferdam Commissioner Company completed concrete Congress construction contracting officer contractor corporation Creek cubic yards December decision defendant defendant's delay drawings dredging employees Engineer entitled to recover excavation filed findings of fact Five Civilized Tribes flour follows funds gift gift tax Government Honduras included income Industrial Recovery Act Judge July June 16 labor lands letter liquidated damages mails March material Medric ment National Industrial Recovery Navy November November 9 October Opinion original Indian title overdepth paid paragraph payment period petition plaintiff proof purchase referred refund Reporter's Statement reservation River rock Secretary Section September shown specifications Stat thereof Tillamooks Tillamooks tribe tion Too-too-to-ney tract tribes and bands trust unratified treaty vessel wages
Popular passages
Page 5 - But no such damages shall be adjusted and paid until thoroughly examined and passed upon by the Commissioner of Indian Affairs and the Secretary of the Interior...
Page 65 - ... due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
Page 433 - Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern.
Page 681 - Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.
Page 575 - Section 2512 provides that if a gift is made in property, its value at the date of the gift shall be considered the amount of the gift.
Page 289 - In addition to other taxes, there is hereby Imposed on every employer an excise tax, with respect to having individuals in his employ...
Page 492 - Nebraska, or to affect the authority of the government of the United States to make any regulation respecting such Indians, their lands, property, or other rights, by treaty, law, or otherwise, which it would have been competent to the government to make, if this act had never passed.
Page 254 - Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
Page 579 - ... unless before the expiration of such period a claim therefor is filed by the taxpayer.
Page 108 - CHANGES The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following...