Trenton Dam: Constructed 1949-1953 |
From inside the book
Page
... Canal Outlet Works Intake structure : Vertical shaft : 50 feet high Sill elevation : 2710.00 Outlet conduit : 5 feet 6 inches in diam- eter , 208 feet long Outlet pipe : 56 - inch - diameter pipe in horseshoe conduit , 244 feet long ...
... Canal Outlet Works Intake structure : Vertical shaft : 50 feet high Sill elevation : 2710.00 Outlet conduit : 5 feet 6 inches in diam- eter , 208 feet long Outlet pipe : 56 - inch - diameter pipe in horseshoe conduit , 244 feet long ...
Page
... outlets , canal outlet works , and railroad structures are included in chapter III . Chapter IV contains discussions on contract administration and survey work . All phases of construction are discussed in chapter V. Chapter VI is ...
... outlets , canal outlet works , and railroad structures are included in chapter III . Chapter IV contains discussions on contract administration and survey work . All phases of construction are discussed in chapter V. Chapter VI is ...
Page i
... Outlets 15 . General 16 . Abutment structure 17 . Gate and bridge supporting structure 225 23 27 27 ( a ) Design considerations 32 ... Canal Outlet Works 25 . General 26. Intake structure 41 41 Section CONTENTS ( Continued ) 27 . 28 . 29 i.
... Outlets 15 . General 16 . Abutment structure 17 . Gate and bridge supporting structure 225 23 27 27 ( a ) Design considerations 32 ... Canal Outlet Works 25 . General 26. Intake structure 41 41 Section CONTENTS ( Continued ) 27 . 28 . 29 i.
Page iv
... outlet and gate control arrangement 38 17 Assembly and list of parts for 6- by 7-1 / 2 - foot high- pressure gate 40 18 Canal outlet works-- Plan and sections 42 19 Canal outlet works discharge curves 44 20 Pressure conduit of canal outlet ...
... outlet and gate control arrangement 38 17 Assembly and list of parts for 6- by 7-1 / 2 - foot high- pressure gate 40 18 Canal outlet works-- Plan and sections 42 19 Canal outlet works discharge curves 44 20 Pressure conduit of canal outlet ...
Page 1
... outlet works is provided to meet irrigation re- quirements . This outlet works forms the headworks for the Meeker Irrigation Canal . An aerial view of Trenton Dam is shown in figure 1 . The dam is one of the key storage and flood ...
... outlet works is provided to meet irrigation re- quirements . This outlet works forms the headworks for the Meeker Irrigation Canal . An aerial view of Trenton Dam is shown in figure 1 . The dam is one of the key storage and flood ...
Other editions - View all
Common terms and phrases
abutment acre-feet aggregate backfill Berm blanket blockouts Brass Cap BUREAU OF RECLAMATION camber canal outlet cement centerline chute coarse concrete construction Contraction joint contractor control house crushed rock cubic yards cutoff trench dam embankment dam foundation designed discharge eleva emergency gate chamber Figure Float flood control gravel grout high-pressure gates Highway bridge Hitchcock County holes horizontal hydraulic hydrostatic head inlet intake structure layer Limits of special loads located loess material maximum metal Nebr north borrow operation pier Pierre shale piezometer Pipe handrail pounds per square pozzolan PROJ pump radial gate railroad reinforcement relocation Republican River reservoir water surface riprap River outlet Rolled embankment SCALE OF FEET second-feet Settlement point Shale surface SILT silty slope south borrow area special compaction specifications spillway structure steel stilling basin storage Sump Sump pump surface at elevation tests Trenton Dam upstream valve vertical walls water surface elevation
Popular passages
Page 51 - Design, Construction, Inspection and Repair of Unfired Pressure Vessels for Petroleum Liquids and Gases.
Page 99 - yd. cu. yd. lin. ft. lin. ft. lin. ft. Labor and materials by contractor Unit cost
Page 94 - yd. cu. yd. cu. yd. cu. yd. Labor and materials by contractor Unit cost
Page 96 - ft. lin. ft. lin. ft. lin. ft. Labor and materials by contractor Unit cost
Page 100 - cu. yd. Lump sum Lump sum Labor and materials by contractor Unit cost 2.00
Page 99 - 88 89 90 91 92 93 94 Property and pay item description Installing metal pipe, fittings, and valves less than 6 inches in diameter Installing metal pipe, fittings, and valves 6 inches
Page 25 - above the maximum water surface, to prevent the dam from being overtopped by waves. Factors influencing wave height and wave ride-up, including maximum wind velocity, direction and duration, offshore reservoir
Page 98 - ft. Ib. Ib. Ib. Ib. Ib. Ib. Ib. Labor and materials by contractor Unit cost