... metres respectively . And this site had been selected even though another site near Pinola Gad was rejected on account of the same problem , i.e. , it had an over- burden ( loose sediment ) 16 metres and 35.1 metres on its left and ...
... metres respectively . And this site had been selected even though another site near Pinola Gad was rejected on account of the same problem , i.e. , it had an over- burden ( loose sediment ) 16 metres and 35.1 metres on its left and ...
Page 45
... metre is the only reliable one , " and , that “ other methods are to be employed when current metres cannot be used " . And , finally , that " measurements of flow by the current metre method have to be done for at least 30 to 40 years ...
... metre is the only reliable one , " and , that “ other methods are to be employed when current metres cannot be used " . And , finally , that " measurements of flow by the current metre method have to be done for at least 30 to 40 years ...
Page 50
... metres , and the maximum base width is 1100 metres . The top of the dam is at elevation at 839.5 metres above MSL , where it is 20 metres wide and about 575 metres long " . Later , on page 150 it states , that " since it would not be ...
... metres , and the maximum base width is 1100 metres . The top of the dam is at elevation at 839.5 metres above MSL , where it is 20 metres wide and about 575 metres long " . Later , on page 150 it states , that " since it would not be ...
Common terms and phrases
acquired for rehabilitation afforestation agricultural Alaknanda assessment B/C ratio benefit/cost ratio Bhagirathi CAD plan calculated canals cent command area compensation construction crores dam authorities Dam Detailed Project dam project authorities Delhi depreciation Detailed Project Report displaced persons distribution earthquake economic energy engineers environmental estimate expenditure Five Year Plan flood forest Friedrich Naumann Foundation Ganga Ganga canal Government of India Government of Uttar gross value guidelines hectares hydel power increase inputs installed capacity investment irrigation Irrigation and Power irrigation potential irrigation projects lakhs Madhya Pradesh Maharashtra major ment metres million Ness Wadia output paise peaking Planning Commission problem Pune quintals Rabi rainfall receipts reservoir river run-off seismicity Seventh Five Shri social submerged suffering to oustees Sugarcane Table TBVSS TDP authorities Tehri Dam Detailed Tehri dam project Tehri project tion Total utilisation Uttar Pradesh value of produce villages yield Стор