Evaluating the Tehri Dam: An Extended Cost Benefit AppraisalStudy on the controversial dam to be constructed at Tehri, Uttar Pradesh. |
From inside the book
Results 1-3 of 41
Page 77
... Increase in cropped area Cropped area Increase in area ( lakh hectares ) ( lakh hectares ) Before Tehri dam After Tehri dam Rabi Wheat 2.48 3.44 0.96 Barley 0.16 0.25 0.09 Other rabi 2.99 4.43 1.44 Kharif Sugarcane 0.41 0.62 0.21 Total ...
... Increase in cropped area Cropped area Increase in area ( lakh hectares ) ( lakh hectares ) Before Tehri dam After Tehri dam Rabi Wheat 2.48 3.44 0.96 Barley 0.16 0.25 0.09 Other rabi 2.99 4.43 1.44 Kharif Sugarcane 0.41 0.62 0.21 Total ...
Page 118
... increase in the costs of the Tehri dam project , without a reciprocal increase in the benefits from the Tehri dam , the cost efficiency of the ' run - of - river ' scheme has improved and become superior to the original Tehri dam plan ...
... increase in the costs of the Tehri dam project , without a reciprocal increase in the benefits from the Tehri dam , the cost efficiency of the ' run - of - river ' scheme has improved and become superior to the original Tehri dam plan ...
Page 131
... increase in the distance will increase the strategically important " First - Strike - Response- Time " required by the Indian Army outposts , by at least six hours . For the Indian Army divisions on the Chinese border , this increase in ...
... increase in the distance will increase the strategically important " First - Strike - Response- Time " required by the Indian Army outposts , by at least six hours . For the Indian Army divisions on the Chinese border , this increase in ...
Common terms and phrases
acquired for rehabilitation afforestation agricultural Alaknanda assessment B/C ratio benefit/cost ratio Bhagirathi CAD plan calculated canals cent command area compensation construction crores dam authorities Dam Detailed Project dam project authorities Delhi depreciation Detailed Project Report displaced persons distribution earthquake economic energy engineers environmental estimate expenditure Five Year Plan flood forest Friedrich Naumann Foundation Ganga Ganga canal Government of India Government of Uttar gross value guidelines hectares hydel power increase inputs installed capacity investment irrigation Irrigation and Power irrigation potential irrigation projects lakhs Madhya Pradesh Maharashtra major ment metres million Ness Wadia output paise peaking Planning Commission problem Pune quintals Rabi rainfall receipts reservoir river run-off seismicity Seventh Five Shri social submerged suffering to oustees Sugarcane Table TBVSS TDP authorities Tehri Dam Detailed Tehri dam project Tehri project tion Total utilisation Uttar Pradesh value of produce villages yield Стор