Page images
PDF
EPUB

payments

the unliquidated progress within the fair value of the work done on the undelivered portion of the contract. (See also § 1-30.525-1.)

§ 1-30.524-6 Erroneous cost estimates. When liquidation percentages lower than those called for by § 1-30.512-1 are established pursuant to § 1-30.510-2, it may occur that actual costs and future cost of performance are higher than the estimated costs used to establish liquidation rates. In such cases (see paragraph (c) (vi) of the clause presented in § 1-30.510-1(a) and paragraph (c) (iv) of the clause prescribed in § 1-30.5102(a)) appropriate increase of the liquidation percentage will be necessary to adjust for any under-liquidation that may have occurred, to bring the amount of unliquidated progress payments within the limits of paragraph (a) (3) of these clauses, and to assure the adequacy of future liquidations. Increase of the liquidation percentage will also become necessary even though the provisions of § 1-30.512-2 have not been applied in fixing the liquidation percentage, when progress payments are based on costs of direct labor and material only (§ 1-30.510-2) or any limited cost base (§ 1-30.511-5), and actual costs forming the base for progress payments are higher than the estimated eligible costs used in establishing the liquidation per

centage.

§ 1-30.525 Government title.

Since the clauses in § 1-30.510 give the Government title to all of the materials, work in process, and finished goods under contracts after the making of progress payments thereon, care should be taken to assure, to the extent reasonably necessary, that the title to the Government will be free of all encumbrances. The procedure in this respect will necessarily vary with the particular circumstances of individual cases. Ordinarily, in the absence of reason to believe that the Government title may be subject to encumbrance, the contractor's certificate will be relied on. If any arrangements or conditions are found that would impair the contractor's right of disposition of the property affected by the progress payments, appropriate arrangements should be made to establish and protect the Government title. The existence of

any such encumbrance is a violation of the contractor's obligations under the contract.

§ 1-30.525-1 Loss, theft, destruction, or damage.

Paragraph (e) of the clauses presented in §§ 1-30.510-1(a) are not intended to apply to normal spoilage. The risk of loss as to property affected by the Progress Payments clause is on the contractor, except to the extent that by some special provision of the contract (such as that relating to aircraft in the open) the Government shall have expressly assumed the risk of loss. Such express assumption of risk by the Government is not made in the Progress Payments clause, the Default clause, or the Termination clause. Because of problems of administering the contract, especially those connected with property responsibility and inventory control, the risk of loss on property to which the Government holds title because of progress payments must be on the contractor to the same extent that it would be if the contractor held title to the property. This risk of loss carries with it the accompanying duty to repay to the Government the amount of unliquidated progress payments based on cost allocable to lost, stolen, or destroyed property or to the damaged portion of the property. If the Government has expressly assumed particular risks of loss, then, to the extent of such express assumption of risk by the Government, the contractor would not be obligated to repay to the Government the amount of unliquidated progress payments based on costs allocable to such lost, stolen, destroyed, or damaged property. (See, however, paragraphs (c) (v) and (c) (vi) of the clauses prescribed in §§ 1-30.510-1(a) and 130.510-2(a), respectively, as to future payments on the contract after such loss, damage, theft, or destruction.) § 1-30.525-2

property.

Government-furnished

Contract provisions referring to or defining liability for Government-furnished property do not apply to property to which the Government shall have acquired title solely pursuant to the provisions of paragraph (d) of the Progress Payments clauses prescribed in § 1-30.510.

| § 1-30.525-3 Special tooling.

When the contractor furnishes special tooling, pursuant to a special tooling clause in the contract, and such special tooling is not to be delivered to the Government as an end item under the contract, the handling and disposition of such special tooling should be governed by the Special Tooling clause of the contract, even though title to such special tooling is held by the Government pursuant to the Progress Payment clause of the contract.

§ 1-30.525-4 Termination for convenience of the Government.

After the giving of notice of termination under contract provision for Termination for Convenience of the Government, the property to which the Government has title pursuant to the Progress Payments clause and which is a part of termination inventory should be acquired or disposed of in accordance with the provisions of the Termination clause of the contract and of applicable laws and regulations. The acquisition or disposition of such termination inventory shall be governed by the Termination clause, even though title to all or a portion of such inventory is in the Government pursuant to the Progress Payments clause of the contract.

=§ 1-30.525-5 Scrap excess property.

(a) In the course of proper performance of contracts, contractors are permitted to sell or otherwise dispose of current production scrap in the ordinary course of business, notwithstanding the Government's title under the Progress Payments clause. Permission of the contracting officer for such disposal of scrap is not required. With the permission of the contracting officer and on terms approved by him, contractors may also acquire or dispose of materials, inventories, or work in process to which the Government has acquired title pursuant to the Progress Payments clause of the contract, including transfer of such property to other work of the contractor. Proceeds of scrap disposal will be credited against the costs of contract performance. Costs allocable to property, other than scrap, so transferred from the contract will be eliminated from the costs of contract performance, and the contractor shall be required to repay to the Government an amount equal to the un

liquidated progress payments allocable to the property so transferred from the contract.

(b) When (1) the contractor has completed all work called for by the contract, and (2) such work has been delivered to and accepted by the Government, and (3) progress payments made under the contract have been fully liquidated, and (4) the contractor has fully performed all his obligations under the contract (including the making of any payments to which the Government may be entitled under the contract, and including compliance with any other provisions of the contract, such as the Termination clause or the Government-furnished property clause), any excess property remaining is to be regarded as having not been allocated or properly chargeable to the contract under sound and generally accepted accounting principles and practices, and this outside the scope of the Progress Payments clause which would have vested title in the Government. Accordingly, the contractor holds title to such excess property and may deal with it as he desires.

§ 1-30.526 Consideration for progress

payments-awards.

When a Progress Payments clause is included at the inception of a contract, no separate consideration is charged for the Progress Payments clause, and there shall be no provision for interest or other specific charge for progress payments, or for a reduction in payments (other than any agreed discount for prompt payment) by reason of the making of progress payments. The worth of the Progress Payments clause to the contractor is expected to be reflected in one or both of (a) a bid or negotiated price that will be lower than such price would have been if provision had not been made for progress payments, or (b) contract terms and conditions, other than price, that are more beneficial to the Government than they would have been if provision had not been made for progress payments.

[blocks in formation]

tract was entered into without progress payment provision. However, cases do occur (a) in which the actual lead time or preparatory period between the beginning of work and the first delivery substantially exceeds the estimated lead time and in fact runs or will run over 6 months (§ 1-30.503), or (b) in which unusual circumstances bring about unexpected substantial accumulation of predelivery costs having material impact on the contractor's working funds (§ 1– 30.505). These cases may arise from occurrences such as (a) uncertainties or errors in specifications, (b) contract change notices, (c) Government delays in testing, inspection, furnishing of material or equipment, furnishing of stock numbers, packaging or shipping instructions or shipping documents, or completion of contract supplements, (d) stretchouts or stop-work orders, (e) performance difficulties of subcontractors suppliers, and (f) causes beyond the control and without the fault or negligence of the contractor of the kinds mentioned in paragraph (c) of the Default clause provided in § 1-8.707. In these kinds of cases, requests of contractors for amendments to provide progress payments should be considered promptly, in the light of the circumstances then existing. If the circumstances then existing approximate conditions under which progress payments would have been properly provided in conformity with these regulations at contract inception, if the new circumstances had been foreseen, progress payments should be provided by amendment. In this connection see particularly §§ 1-30.202, 1-30.204, 1.30.205, 1-30.206, 1-30.207, 1-30.210, 1-30.210-1. and 1-30.528.

§ 1-30.528 Consideration for amendments providing for progress pay

ments.

Contracts may not be modified except in the interest of the Government. Contracts which do not provide for progress payments may be amended to provide for progress payments only when the amendment provides new and valuable consideration moving to the Government. Appropriate price reduction may

provide this consideration. In the varying circumstances of individual cases, the consideration for progress payments need not necessarily be monetary. Agreements by the contractor, incorporated in such an amendment, for the benefit of and substantially advantageous to the Government, may constitute sufficient consideration for an amendment providing for progress payments. When estimated financing costs have been included as an element (whether or not identified) in the contract price of a contract not providing for progress payments, it is fair to expect elimination of the applicable portion of that element of the price when progress payments are provided by amendment. The fair and reasonable consideration for the progress payment amendment should approximate in value as nearly as practically ascertainable the amount by which the contract price would have been smaller if a Progress Payments clause had been contained in the contract in the first instance. In the absence of definite information on this point, pertinent factors for estimating the fair and reasonable amount of consideration would include (a) the amounts of progress payments expected to be outstanding for an estimated period of time, (b) the cost of equivalent working funds to the contractor, and (c) the estimated profit rate expected to be earned by contract performance. If not accomplished by a contract price reduction, other concessions or agreement by the contractor, advantageous to the Government and incorporated in the amendment, may be fairly evaluated and accepted as being of value reasonably equivalent to a price reduction. This consideration should be such as is fair, equitable and reasonable in the light of the circumstances of each case. (See § 1-30.527.) This consideration should be for the progress payment amendment, and their shall be no provision for interest or other specific charge for progress payments, or for a reduction in payments after the progress payment amendment (other than any agreed discount for prompt payment) by reason of the making of progress payments.

[merged small][merged small][merged small][graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

(b) Page 2 of Format 529.

INSTRUCTIONS

SECTION 1 IDENTIFICATION INFORMATION Complete items 1 through G in accordance with the following instructions:

ITEM I TO Enter the name and address of the contracting officer or his representative.

ITEM 2 FROM CONTRACTOR'S NAME AND ADDRESS Enter the name and mailing address of the contractor.

ITEM 30 TOTAL CONTRACT PRICE Enter the total contract price, as amended. If the contract provides for price redetermination, enter the initial price until changed; if the contract is of the incentive type, enter the target price until changed; not the ceiling or maximum price. For letter contracts, enter the maximum expenditure authorized by the contract, as amended.

ITEM 36 CONTRACT PRICE OF ITPMS TO BE DELIVERED AND/OR ACCEPTED Enter the total billing price of the undelivered items and/or of delivered items not yet accepted and invoiced under the contract.

ITEM CONTRACT NUMBER Enter the number of the contract on which progress payment is being requested.

ITE 5 INVOICE NUMBER AND DATE Enter the number and date of the Invoice for the progress payments requested herein. If no invoice is submitred herewith, enter "none".

ITEN 60 Enter the number assigned to this request. All requests under single contract must be numbered consecutively beginning with 1. Each subsequent request under the same contract must continue in sequence the same series of numbers without emission or duplication.

ITEM 68 Enter the date of this request.

ITEM 6c Enter the amount of progress payment requested herein, which should not exceed the amount shown in item llc.

SPCTION II GENERAL INSTRUCTIONS DATES Spaces are provided in the heading of Section II for the entry of two dates. In the firet space, enter the date of the first incurrence of coms of performance of the kind eligible for progress payments under the contract. In the second space, enter the dare through which such costs have been accumulared for inclusion in this request and are therefore shown individually, as applicable item entries in Sections II and III.

LIMITED COSTS BASIS Cenain contracto limit the progress payment base to incurred coate of direct labor and/or direct marerial or other specified coste which are less than incured "Total costs". Then the contract includes such limitations only those costs eligible for progress payments under contract are to be identified and reported in Section II.

ITEM-1-11 applicable, enter the rate werd in computing general and administrative expenses and the computed dollar amount.

ITEM 7 Self-explanatory.

ITEM Enter the percentage figure for progress payments stated in the contract (Paragraph (a) (1) (1) of the uniform progress payment clause) and the computed dollar amount based on that percentage, ie., the com puted dollar amount of the entry in hem 78.

ITEMS AND 10 Make no entry unless the contract requires progress payments to the contractor on account of progress payments to sub contractors. Include only progress payments on subcontracts which ass form to the progress Dayment provisions of the prime contract.

ITEM. Enter only progress paymento actually paid.
ITEM. Enter total progress payments recouped from subcontractors.
ITEN C. Self-explanatory.

ITEM.d. Make no entry unless the prime contract specifies progress payment on account of unpaid subcontract progress payment billinge which have been approved for current payment in the ordinary course of business. Include only such approved unpaid invoices.

ITEK 10-Self-explanatory.

ITEM 11. Self-explanatory.

ITEM 11- Enter the percentage stated in the contract which limits aggregate progress payments (Paragraph (a) (4) of the uniform progress payment clause) which can be made and compute the dollar amount based on that percentage, i.e., the computed dollar amount of the entry in isem Ja.

ITEN 11c Self-explanatory.

ITEMS 12 AND 13 Self-explanatory.

[graphic]

GENERAL INSTRUCTIONS This section is to be com plered only when specifically requested by Government personnel re sponsible for administration of the contract. Completion of this see tion will be requ when the rate or quality of contract performance is not hen there is reason to believe that: (a) the pas to the contractor; or (b) insufficient com delivered items; or (c) outstanding progress pay fair value of the work accomplished on the ponti of the contract or (2) the applicable percentage of located to unfinished work.

SPECIMEN

TOTAL COST BASIS Certain contracta provide that
bese will be total incurred costs. In such case from!)
penoco incurred for performance of the contract
cable to the contract, consistent with sound and

epted account auded by the con tract. (For exclusions, see the progress payment clad of the contract.)

ing principles and practices, and which are not othe

MANUFACTURING AND PRODUCTION EXPENSE: GENERAL AND ADMINIS TRATIVE EXPENSE Under certain conditions, eligible incurred costs inclade manufacturing and production expenses and general and administrative expenses which have been incurred for performance of the contract which are reasonable, allocable to the contract, and consistent with sound and gen erally accepted accounting principles and practices.

(NOTE: In connection with the first progress payment request on a contract, attach an explanation of the method, bases and period used in detennining the amount of each of these two types of expenses. It the method, bases or periods used for computing these expenses dif for in subsequent requeste for progress paymente under the contract, artech an explanation of such changes to the progress payment re queer involved.)

INCURRED COSTS INVOLVING SUBCONTRACTORS If the incurred costs eligible for progress payments under the contract include costs shown on invoices of subcontractors, suppliers and others that portion of the costs computed on the basis of such invoices can only include coars for: (1) completed work to which the prime contractor has acquired title; (2) materi als delivered to which the prime contractor has acquired tide; (3) services rendered, and (4) costs billed under cost reimbursement or time and materi al subcontracts for work to which the prime contractor has acquired title.

SECTION 11 SPECIFIC INSTRUCTIONS

ITEM 7 COSTS & LIGIBLE UNDER PROGRESS PAYMENT CLAUSE. Coste to be shown in items 70 through 78 are not to include advance payments, dow payments, deposits, or progress payments made or to be made to subcos tractors, suppliers or others.

ITEM 7. and b If applicable, enter the direct material and direct labore COBLA.

ITEM 7c. If applicable, enter the rate used in computing manufacturing and production expenses and the computed dollar amount.

ITEM 7 d. Kater the total of all other direct coms. Attach a separate statement identifying each such cost and the amount thereof.

ITEM 7. Self-explanatory.

SECTION 1 SPECIFIC INSTRUCTIONS

ITEM 14 Of the costs reported in Item 78, compute and enter only costs which are applicable to items delivered, invoiced and accepted to the applicable date. In order of preference, these costs are to be computed on the basis of one of the following: (a) the actual unit coat of items delivered, giving proper consideration to the defermer of the starting lead costs; (b) projected unit costs (based on experienced costs, plus gatimered coats to complete the contract), where the cootractor maintains cost data which will clearly establish the reliability of such varimares; and (e) the total contract price of items delivered.

[blocks in formation]
« PreviousContinue »