Mississippi River Flood Control, Morganza Floodway: Hearings Before the Committee on Commerce, United States Senate, Seventy-fifth Congress, Third Session on S. 3354, a Bill to Amend the Act Entitled "An Act to Amend the Act Entitled 'An Act for the Control of Floods on the Mississippi River and Its Tributaries ... " |
From inside the book
Results 1-5 of 22
Page 3
... stage : Provided further , That if the Chief of Engineers finds that it has been or will be necessary or advisable to change the location of any such flood - control work in order to provide the protection contemplated by this section ...
... stage : Provided further , That if the Chief of Engineers finds that it has been or will be necessary or advisable to change the location of any such flood - control work in order to provide the protection contemplated by this section ...
Page 30
... stage corresponding to 51 feet on the Vicksburg gage has been reached , and not then if anticipated stages indicate that the use of the floodway will not be necessary . What was the flood stage at Vicksburg in the flood of 1937 ? Major ...
... stage corresponding to 51 feet on the Vicksburg gage has been reached , and not then if anticipated stages indicate that the use of the floodway will not be necessary . What was the flood stage at Vicksburg in the flood of 1937 ? Major ...
Page 31
... stage , you would have to change the law . Representative WHITTINGTON . I read further from the committee document , General Schley [ reading ] : and not then if anticipated stages indicate that the use of the floodway will not be ...
... stage , you would have to change the law . Representative WHITTINGTON . I read further from the committee document , General Schley [ reading ] : and not then if anticipated stages indicate that the use of the floodway will not be ...
Page 36
... stages up beyond Natchez . by almost a similar amount . Not that particular year , but as it wears down its bed . So at Angola the Morganza outlet is a definite part of any plan for lowering the flood plane of the river . Senator ...
... stages up beyond Natchez . by almost a similar amount . Not that particular year , but as it wears down its bed . So at Angola the Morganza outlet is a definite part of any plan for lowering the flood plane of the river . Senator ...
Page 48
... stage , this area , which was once a most valuable asset to this city , was subjected to periodical overflows , and increased washing of the same has now practically destroyed it . So much as remains is yet , for the reason above ...
... stage , this area , which was once a most valuable asset to this city , was subjected to periodical overflows , and increased washing of the same has now practically destroyed it . So much as remains is yet , for the reason above ...
Other editions - View all
Common terms and phrases
75 percent acres ALLEN alluvial valley Angola Arkansas City Arkansas River Atchafalaya Basin Atchafalaya River authorized back protection levee Baton Rouge Bonnet Carre Brigadier General FERGUSON built capacity carry Chairman Chief of Engineers committee condemnation Congress construction cubic feet cut-offs diversion easements Eudora floodway Eudora spillway feet per second flowage easements flowage rights freeboard fuse fuseplug levee gage give Government Governor LECHE grade and section GRUBS HAMLEY HEBERT JACOBS KLORER land levee board levee district Louisiana Louisiana line Major General SCHLEY middle section miles Mississippi River Commission Morganza floodway Morganza spillway Natchez necessary Orleans Overton Act Overton bill Parish plug Pointe Coupee Parish police jury problem question Red River Representative WHITTINGTON reservoirs rights-of-way Senator BILBO Senator MILLER Senator OVERTON Senator OVERTON presiding Senator SHEPPARD side statement SUMMERLIN superflood tion Total number Total value United Vicksburg West Atchafalaya
Popular passages
Page 2 - Act shall be expended on the construction of any project until States, political subdivisions thereof, or other responsible local agencies have given assurances satisfactory to the Secretary of War that they will (a) provide without cost to the United States all lands, easements, and rights-of-way necessary for the construction of the project...
Page 1 - That the following sums of money be, and are hereby, appropriated, to be paid out of any money in the Treasury not otherwise appropriated, to be immediately available, and to be expended under the direction of the Secretary of War and the supervision of the Chief of Engineers, for the construction, completion, repair, and preservation of the public works hereinafter named: ***** Sec.
Page 10 - An Act for the control of floods on the Mississippi River and its tributaries, and for other purposes...
Page 3 - The 1928 act authorized $5,000,000 which has been exhausted and the 1936 act authorized $15,000,000 to replenish these funds to be allocated by the Secretary of War on the recommendation of the Chief of Engineers in rescue work or in the repair and maintenance of any flood-control work on any tributaries of the Mississippi River threatened or destroyed by flood heretofore or hereafter occurring.
Page 2 - That hereafter no money appropriated under authority of this Act shall be expended on the construction of any project until States, political subdivisions thereof, or other responsible local agencies have given assurances satisfactory to the Secretary of War...
Page 165 - Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the project for the flood control of the Mississippi River in its alluvial valley...
Page 165 - The plan is a comprehensive one, providing for the maximum flood predicted as possible, and for future expansion to meet changing conditions. It includes a spillway above New Orleans, diversion floodways in the Atchafalaya and Tensas Basins, a river bank floodway from Cairo, Illinois, to New Madrid, Missouri, together with strengthening and a moderate raising of existing levees.
Page 2 - River, hereby authorized, shall be undertaken until the States, or other qualified agencies, shall have furnished satisfactory assurances that they will undertake, without cost to the United States, all alterations of highways made necessary because of the construction of the authorized reservoirs, and meet all damages because of such highway alterations, and have agreed also to furnish without cost to the United States all lands and easements necessary to the construction of levees and drainage...
Page 2 - Chiaf of Engineers, with the approval of the Secretary of War, may modify the project for the flood control of the Saint Francis River as recommended in said report, to include therein the construction of a detention reservoir for the reduction of floods, and the acquisition at the cost of the United States of all lands and flowage necessary to the construction of said reservoir except flowage of highways...
Page 3 - States free from damages due to the construction works; (c) maintain and operate all the works after completion in accordance with regulations prescribed by the Secretary of the Army...