... written notice to the contractor, to provide any such labor or materials, and to deduct the cost' thereof from any money then due or thereafter to become due to the contractor under... The New York Supplement - Page 2181909Full view - About this book
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - Law reports, digests, etc - 1919 - 806 pages
...refusal, neglect or failure being certified by the architect, the owners shall be at liberty, after three days' written notice to the contractor, to provide...to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action,... | |
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - Law reports, digests, etc - 1916 - 804 pages
...neglect or failure being certified by the architect, the owner shall be at liberty after 48 hours' written notice to the contractor to provide any such...thereafter to become due, to the contractor, under the contract, and if the architect shall certify that such refusal, neglect or failure is sufficient... | |
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - Law reports, digests, etc - 1898 - 796 pages
...the architect, the owners shall be at liberty, after three days' written notice to the contractors, to provide any such labor or materials, and to deduct...money then due, or thereafter to become due, to the contractors under this contract." " It is hereby mutually agreed between the parties hereto that the... | |
| Marcus Tullius Hun - Law reports, digests, etc - 1893 - 724 pages
...the architect, the owner shall be at liberty, after three days' written notice to the contractors, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractors under this contract. And if the architect shall certify that such refusal, neglect or failure... | |
| Law reports, digests, etc - 1922 - 1138 pages
...refusal, neglect, or failure being certified by the architect, the owner shall be at liberty, after three days' written notice to the contractor, to provide...to the contractor under this contract, and if the architect <f;=For other cases see same topic and KEY-NUMBER in all Key-Numbered DlgesU and Indexe»... | |
| Law reports, digests, etc - 1912 - 1170 pages
...neglect or failure being certified by the architect, the owner shall be at liberty after five days (5) written notice to the contractor, to provide any such...to the contractor under this contract ; and If the architect shall certify that such refusal, neglect or failure Is sufficient ground for such action,... | |
| Law reports, digests, etc - 1913 - 1236 pages
...written notice to the contractor, to provide any such labor and materials, and to deduct the costs thereof from any money then due, or thereafter to...that such refusal, neglect, or failure is sufficient grounds for such action, the owner shall also be at liberty to terminate the employment of the contractor... | |
| Law reports, digests, etc - 1914 - 1230 pages
...liberty, after three days' written notice to the contractors, to provide all such labor or materials and deduct the cost thereof from any money then due or thereafter to become due the contractors under this contract ; and if the architects shall certify that such refusal, neglect... | |
| Law reports, digests, etc - 1895 - 1150 pages
...the architect, the owner shall be at liberty, after three days' written notice to the contractors, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractors under this contract; and, if the architect shall certify that such refusal, neglect or... | |
| Law reports, digests, etc - 1908 - 1148 pages
...refusal, neglect, or failure being certified by the architect, the owner shall be at liberty after ten days' written notice to the contractor to provide...to the contractor under this contract. And, If the architect shall certify that such refusal, neglect, or failure is sufficient grounds for such action,... | |
| |