Page images
PDF
EPUB

Mr. BOLAND. This request is for $3 million for fiscal 1962.
There are no questions on this item.

NAVARRO MILLS RESERVOIR

Navarro Mills Reservoir.

Mr. Reporter, will you please insert at this point pages 168 through 173.

(Pages 168 through 173 of the justifications are as follows:)

NAVARRO MILLS RESERVOIR, TEXAS (Continuing)

LOCATION: In the western portion of Navarro County, Texas on Richland Creek at river mile 63.9 and about 16 miles southwest of Corsicana, Texas.

[blocks in formation]

1 In addition, local interests are required to reimburse the Federal Government for costs allocated to water supply storage, in 40 annual installments beginning 1 January 1970. This reimbursement is presently estimated about $2,400,000, exclusive of interest.

Dam:

Type...Rolled Earth Fill

PHYSICAL DATA

Reservoir Capacity: Flood Control

143,200 acre-feet

[blocks in formation]

Height..82 feet (Maximum above stream bed)

Length..7,570 feet (including spillway)

[blocks in formation]

NAVARRO MILLS RESERVOIR, TEXAS (Cont'd)

STATUS (1 January 1961)

[blocks in formation]
[blocks in formation]

JUSTIFICATION:

The project will provide substantial flood protection to about 41,100 acres of agricultural
land in the flood plain of Richland Creek below the dam site, and protection to a lesser degree to about
The last serious flood
452,000 acres in the Trinity River flood plain below the mouth of Richland Creek.
occurred during April-May 1958 and caused damages amounting to approximately $3,645,000, at then prevailing
A recurrence of this flood under present
prices, in the flood plains that would be benefited by the project.
conditions of development and price levels would cause damages estimated at $4,410,000 of which $618,000
The project will also provide a dependable source of water supply.
would be prevented by the project.

FISCAL YEAR 1962: The requested amount of $3,500,000 will be applied to:

1

Continue acquisition of lands

585,000

Complete relocation of West Texas Gulf pipeline

501,300

Complete relocation of county roads

320,800

Complete relocation of FM road 639

127,800

Complete relocation of FM road 744

364,400

Complete relocation of telephone and electric lines

19,000

Complete reservoir clearing

107,700

Initiate second stage embankment

250,000

Continue construction of spillway

750,000

Initiate recreation facilities

115,000

Continue buildings, grounds, and utilities

70,300

Continue permanent operating equipment

34,000

Engineering and Design

60,200

Supervision and Administration

Funds requested for FY 1962 are considered to be the minimum amount required in order to maintain an economical coordination of construction phases.

194,500

TOTAL

$3,500,000

NAVARRO MILLS RESERVOIR, TEXAS (Cont'd)

NON-FEDERAL COSTS: The authorizing acts stipulate that prior to construction of the project local interests must provide assurances satisfactory to the Secretary of the Army that they will: (a) pay an amount equal to 25 per cent of the total cost of the project for the conservation storage space provided in the reservoir; (b) pay an amount of $300,000 for increase in utilization of the downstream valley lands; and (c) assume 25 per cent of the annual cost of maintenance and operation of the project.

The local interests, represented by the Trinity River Authority, desire to acquire rights to the conservation storage space in the project under the provisions of the Water Supply Act of 1958, and a contract was negotiated on this basis. The allocated cost of the conservation storage space, presently estimated about $2,400,000 (excluding interest during construction), will be paid for in 40 annual installments beginning 1 January 1970. The contract provides for adjustment of annual payments on the basis of final project costs. The Authority also will contribute $300,000 during the period of construction for increase in net returns from higher land utilization. In addition, the Authority will pay 25 per cent of the cost of sedimentation resurveys, major capital replacements, and the annual experienced cost of operation and maintenance of the project (exclusive of the operation and maintenance cost for land management and public utilization).

STATUS OF LOCAL COOPERATION: A formal contract with the TRA embodying the requirements of local cooperation was approved by the Secretary of the Army on 27 August 1959.

COMPARISON OF FEDERAL COST ESTIMATES: The current Federal cost estimate of $9,700,000 is a decrease of $400,000 from the latest estimate (10,100,000) submitted to Congress. This decrease includes $450,000 in construction features due to detailed engineering studies and savings on awarded contract and $58,000 for Supervision and Administration based on a reanalysis of requirements. The decrease was partially offset by an increase of $32,000 for lands and damages and $76,000 for an estimated price level rise in construction features.

[graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]
« PreviousContinue »