Page images
PDF
EPUB

Accumulated % of Estimated Fed.(CofE) Cost

ICE HARBOR LOCK AND DAM WASHINGTON (Continuing)

LOCATION: On the Snake River, 9.7 miles above confluence with Columbia River, approximately 12 miles east of Pasco, Washington.

AUTHORIZATION: 1945 River and Harbor Act

BENEFIT/COST RATIO: 2.1 to 1 for initial power installation

SUMMARIZED FINANCIAL DATA

Estimated Federal Cost (Corps of Engineers) 1/ $121,000,000 Estimated Federal Cost (U. S. Coast Guard)

87,000

Appropriations to 30 June 1960 Appropriations for FY 1961

$ 87,337,000

Estimated Non-Federal Cost

Cash Contributions

82,500

Appropriations to date

25,463,000 $112,800,000

93

Other Costs

$82,500
0

Appropriations requested for FY 1962

$ 8,200,000 100

[blocks in formation]

Estimated Federal Cost (Corps of Engineers) 1/ $142,800,000 (Ultimate Installation)

Balance to complete after FY 1962

1/ Exclusive of deferred construction on relocations estimated to cost $1,000,000.

[blocks in formation]

ICE HARBOR LOCK AND DAM, WASHINGTON (Continued)

[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

Relocations

75

23

Land Acquisition

May 1962
May 1962

Relocations

Oct 1961

First Stage Construction, including construction of first step cofferdam required for powerhouse, fish facilities and dam

[blocks in formation]

on left (south) bank, left abutment, powerhouse intake, and
substructure, 71⁄2 bays of spillway dam, south shore fish
passage facilties, project roads and railroads

90,000 kw each)

Dec 1961

[merged small][subsumed][ocr errors][subsumed]
[ocr errors]

Second Stage Construction, including construction of second
step cofferdam, navigation lock, fish facilities on right
(north) bank, 2 bays of spillway dam and right abutment
Completion of Powerhouse, including superstructure and
installation of equipment
Procurement of 3

143,000 HP turbines, 3 90,000 kw generators,
main transformers for 3 units, governors for 3 turbines and
associated accessory electrical and miscellaneous power plant
equipment

78

ICE HARBOR LOCK AND DAM,

JUSTIFICATION:

WASHINGTON (Continued)

Ice Harbor Lock and Dam provides for an initial installation of 270,000 kilowatts of generating capacity and is the farthest downstream of four authorized multiple-purpose dams to provide slack-water navigation, hydroelectric power, and other beneficial water-use development on the lower Snake River. The project is an essential unit in the authorized slack-water navigation and hydroelectric power development of lower 360 miles of Columbia River and the lower 140 miles of Snake River.

Estimates shown in the Bonneville Power Administration Power Outlook 1960-70 indicate that Pacific Northwest regional resources now existing and under construction, including Ice Harbor, will meet system firm energy demand in the winter season of 1962-63, the first full season of power production for Ice Harbor. Continual development of additional resources will be required to keep pace with prospective power demands in the Pacific Northwest region; and power shortages, if they occur, will retard industrial and other development essential to regional economic growth.

The development of navigation on Snake River will extend the Columbia-Snake River authorized waterway. It is estimated that about 2,600,000 tons of commerce would move annually on and through the Ice Harbor pool after all four of the lower Snake River projects are completed. An additional 1,400,000 tons is expected to develop from the Lime Point area after the proposed Asotin project is completed. Commerce on the Ice Harbor pool will be principally bulk commodities such as wheat, wood products, limestone, ores, petroleum and fertilizers.

The development of Ice Harbor Lock and Dam as a unit of the slack-water plan on Snake River will provide for early shipping of grain and receiving of petroleum and fertilizer products. The project will extend the waterway influence or tributary shipping area some 60 to 75 miles above the head of the project pool.

The project will also reduce pumping lifts for irrigation developments along the reservoir shore line and will provide incidental recreational benefits.

70856 0-61-pt. 1-31

ICE HARBOR LOCK AND DAM,

WASHINGTON (Continued)

FISCAL YEAR 1962: The amount of $8,200,000 will be applied as follows:

Complete acquisition of lands

Continue Northern Pacific Railway Embankment Protection

[blocks in formation]

Complete reservoir clearing

100,000

[blocks in formation]

70,000

Complete construction of dam, navigation lock, fish facilities, powerhouse and installation of equipment

3,800,000

Complete procurement of turbines, generators, accessory and miscellaneous power plant equipment
Complete dredging downstream navigation channel

[blocks in formation]

Complete procurement of permanent operating equipment

80,000

Complete construction of permanent buildings and utilities
Complete construction of recreation facilities
Cofferdam removal and field facilities
Engineering and Design

Supervision and Administration

[blocks in formation]

TOTAL

The funds requested for Fiscal Year 1962 will complete the project except for deferred construction work.
NON-FEDERAL COSTS: None

STATUS OF LOCAL COOPERATION:

None required.

$8,200,000

COMPARISON OF FEDERAL COST ESTIMATE: The current Federal (Corps of Engineers) cost estimate of $121,000,000 is a decrease of $4,000,000 from the latest estimate ($125,000,000) submitted to Congress. Changes which contributed to reductions in the estimate included net decreases of $1,613,000 for more detailed design and investigations, $874,000 due to favorable bids and negotiations for agreements, $3,254,000 for reduction of contingencies, $1,000,000 for exclusion of deferred construction costs estimated to be required for relocations following completion of the project, and $710,000 in Supervision and Administration based on costs to date and estimated future requirements. These reductions were partially offset by increases of $170,000 for higher price levels, $3,121,000 for overruns on existing contracts, and $160,000 for Engineering and Design based on costs to date and a reanalysis of future requirements.

[graphic][subsumed][subsumed][merged small][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]
« PreviousContinue »