Trenton Dam: Constructed 1949-1953 |
From inside the book
Results 1-2 of 2
Page 23
... freeboard . To allow for settlement of the foundation and consolidation of the embankment without a reduction in freeboard , a camber was provided over the crest length . From a maximum camber of 1.5 feet , anticipated settlement and ...
... freeboard . To allow for settlement of the foundation and consolidation of the embankment without a reduction in freeboard , a camber was provided over the crest length . From a maximum camber of 1.5 feet , anticipated settlement and ...
Page 33
... freeboard will exist under maximum discharge conditions . Counterfort walls extend downstream from spillway station 36 + 75 . These were analyzed for the same stability and base pressure criteria as the cantilever walls . The uplift ...
... freeboard will exist under maximum discharge conditions . Counterfort walls extend downstream from spillway station 36 + 75 . These were analyzed for the same stability and base pressure criteria as the cantilever walls . The uplift ...
Other editions - View all
Common terms and phrases
accessory cut-off trench acre-feet Approach channel Axis backfill Berm blanket Blockout BUREAU OF RECLAMATION canal outlet centerline channel capacity coarse concrete conduit construction Contraction joint Counterweight crushed rock cutoff trench dam embankment designed discharge drain outlet emergency gate chamber Expansion joint Figure Float flood control floor gate structure gravel ground surface Grouted high-pressure gate Highway bridge holes horizontal hydraulic hydrostatic head inlet installed intake structure Limits of special load located loess material maximum Metal Nebr NORTH BORROW AREA Pierre shale piezometer Pipe handrail PROJ Radial gate railroad reinforcement relocation Republican River reservoir water surface riprap River outlet Rolled embankment SCALE OF FEET second-feet SECTION A-A Settlement point Shale surface Sheet SILT silty slope special compaction spillway crest spillway gates spillway structure steel stilling basin Stoplog storage Sump Sump pump surface at elevation surfaces where directed Trashrack structure Trenton Dam upstream vertical walls water surface elevation